Field Work and Construction Updates

Updated January 27, 2017: With major construction work now complete, there will no longer be a weekly Field Work Notice. Notices will be posted in 2017 if important field work is scheduled.

Sellwood Bridge Field Work Notice – December 22, 2016

Sellwood Bridge in fog from the eastbank

Field Work Notice - December 22, 2016

As construction work wraps up, the contractor is working on clean-up tasks throughout the project area. The field work notice will focus on major work items rather than these clean-up tasks. With the short work week next week, we do not expect to send out the next notice until after Jan. 2.

TRAFFIC ALERTS

  • Hwy. 43 Interchange: One of two lanes on the northbound ramp from the bridge to Hwy. 43 is closed Dec. 22 from 9 am until early afternoon while a manhole cover is adjusted.
(more)

Sellwood Bridge/Hwy. 43 traffic alert (12/21-12/22)

Project Notice - December 21, 2016

One lane of Hwy. 43 will be closed under the west end of the Sellwood Bridge on Wednesday, Dec. 21 from 9 am until as late as 3 pm while a subcontractor removes equipment from the work zone. Flaggers will direct traffic on the open lane.

On Thursday, Dec. 22, one lane on the northbound onramp from the bridge to Hwy. 43 will be closed from 9 am until early afternoon while a manhole height is adjusted. One lane will remain open on the ramp.


Sellwood Bridge Field Work Notice – December 16, 2016

Sellwood project trailers bid farewell

Field Work Notice - December 16, 2016

As construction work wraps up, the contractor will be working on clean-up tasks throughout the project area. The field work notice will focus on major work items rather than these clean-up tasks.

WEST SIDE WORK

New Bridge and Interchange: A pedestrian hand railing will be installed along the sidewalk of the southeast interchange ramp next week.

Multiuse Path Bridge: A protective bar is being placed at the bottom of the fence on this bridge that will carry bicyclists and pedestrians from the regional trail under the main bridge to reach its south sidewalk.

(more)

Sellwood Bridge Field Work Notice - December 9, 2016

TriMet service returned to the Sellwood Bridge this week for first time in 12 years.

Field Work Notice - December 9, 2016

As construction work wraps up, the contractor is working on clean-up tasks throughout the project area. At times workers will be out on the bridge or around the roadway. Traffic cones and warning signs will be put up if work affects traffic. Field work notices will focus on major work rather than clean-up tasks.

TRAFFIC ALERTS

  • SW Terwilliger Closure: SW Terwilliger Blvd. is closed south of the Sellwood Bridge from Hwy. 43 in Lake Oswego to SW Castleridge for a sewer project. The closure will last up to eight months. Visit the project website for recommended detours.
  • Speed, weight and vehicle length limits changing: The speed limit on the bridge has increased to 30 mph and the speed limit on Hwy. 43 near the bridge returned to 35 mph. The 30-foot vehicle length limit on the bridge has been eliminated. Signs for the new vehicle weight limit on the bridge will be posted in December.
  • TriMet service returns: TriMet bus service has returned to the Sellwood Bridge after a 12-year absence. Line 99 provides weekday rush hour service across the bridge, connecting the east side with westside destinations from Lake Oswego to downtown Portland. Read the news on TriMet’s website.
  • Changes for 6th/Tacoma Signal: The traffic signal phases for north and south-bound movements on SE 6th Ave. will be combined to improve east-west traffic flow on Tacoma St. The signal change should be made in the next month. Signs will be installed to prevent right turns on red for westbound traffic on Tacoma and northbound traffic on 6th.
(more)

Sellwood Bridge Field Work Notice - December 1, 2016

At left, a bridge for bicyclists and pedestrians will connect the west trail to south sidewalk of Sellwood Bridge.

Field Work Notice - December 1, 2016

As construction work wraps up in the coming weeks, the contractor will be working on clean-up tasks throughout the project area. The field work notice will focus on major work items rather than these clean-up tasks.

TRAFFIC ALERTS

  • Speed, weight and vehicle length limits changing: The speed limit on the bridge has increased to 30 mph and the speed limit on Hwy. 43 near the bridge returned to 35 mph. The 30-foot vehicle length limit on the bridge has been eliminated. Signs for the new vehicle weight limit on the bridge will be posted in December.
  • TriMet service returns Dec. 5: TriMet bus service returns to the Sellwood Bridge after a 12-year absence on Dec. 5, when Line 99 resumes weekday rush hour service across the bridge. The service will connect the east side with destinations from Lake Oswego to downtown Portland. Read all the news on TriMet’s website.
  • Bridge Sidewalk: The south sidewalk opened for use on November 29.
  • Changes for 6th/Tacoma Signal: The traffic signal phases for north and south-bound movements on SE 6th Ave. will be combined in December to improve east-west traffic flow on Tacoma St. Signs will be installed to prevent right turns on red for westbound traffic on Tacoma and northbound traffic on 6th.
(more)

Sellwood Bridge Field Work Notice - November 23, 2016

The west path bridge to south bridge sidewalk opens in December.

The west path bridge to south bridge sidewalk opens in December.

Field Work Notice

TRAFFIC ALERTS

  • Speed, weight and vehicle length limits changing: The speed limit on the bridge has increased to 30 mph and the speed limit on Hwy. 43 near the bridge returned to 35 mph. The current 30-foot vehicle length limit on the bridge will be eliminated when signs are removed next week. Signs for the new vehicle weight limit on the bridge will be posted later in December.
  • TriMet service returns Dec. 5: TriMet bus service returns to the Sellwood Bridge after a 12-year absence on Dec. 5, when Line 99 resumes weekday rush hour service across the bridge.  The service will connect the east side with destinations from Lake Oswego to downtown Portland. Read all the news on TriMet’s website.
  • Springwater Trail is open: The trail reopened this week between SE Spokane St. and SE Umatilla St. after being repaved.
  • Spokane St. parking reopens: On-street parking has reopened on Spokane west of Oaks Park Way after paving work was completed.
  • Bridge Sidewalks:  The north bridge sidewalk reopened after painting work below the bridge was completed.  The south sidewalk is expected to open the week of Nov. 28.
  • Changes for 6th/Tacoma Signal:  The traffic signal phases for north and south-bound movements on SE 6th Ave. will be combined to improve traffic flow for east-west traffic on Tacoma St.  The signal change could be made as soon as Nov. 30.  Signs will be installed to prevent right turns on red for westbound traffic on Tacoma and northbound traffic on 6th.
(more)

Sellwood Bridge Field Work Notice – November 18, 2016

Springwater Trail repairs below Sellwood Bridge

Springwater Trail repairs below Sellwood Bridge

Field Work Notice - November 18, 2016

TRAFFIC ALERTS

  • TriMet service returns after 12 years! TriMet bus service returns to the Sellwood Bridge after a 12-year absence on Dec. 5, when Line 99 resumes weekday rush hour service across the bridge.  The service will connect the east side with destinations from Lake Oswego to downtown Portland.  Bus service ended in 2004 due to reduced weight limits on the old bridge.  Read all the news on TriMet’s website.
  • Springwater Trail: The trail is closed between SE Spokane St. and SE Umatilla St. for repairs and paving. Trail users are being detoured to 6th Ave.  It is expected to reopen by Nov. 23, weather permitting.
  • Hwy. 43 Lane Closures: The center lanes will be closed near the bridge during offpeak hours on Nov. 18 while crews adjust the height of manhole covers.
  • Spokane St.: There will be no on-street parking on Spokane west of Oaks Park Way from 6 am on Nov. 18 until Nov. 19, during paving.
  • North sidewalk closure: A section of the north bridge sidewalk is closed until Nov. 23 (estimate) while the contractor uses the sidewalk to work on the outside of the bridge structure below. Sidewalk users are using ramps to access a protected path that will be separated by a buffer zone from the westbound traffic lane.
  • Changes for 6th/Tacoma Signal:  Several changes are being made to improve traffic flow through the new traffic signal. North and south-bound movements on SE 6th Ave. currently have separate signal phases.  The two phases will be combined to provide more time for the primary east-west flow on Tacoma St.  More striping, a bike box, and signage changes will also be added to improve traffic flow.
(more)

Sellwood Bridge Construction Traffic Impacts, Nov. 17-23

Project Notice - November 17, 2016

The Sellwood Bridge construction project will impact traffic in several locations November 17-23:

  • Highway 43: There will be closures of the north and southbound center lanes near the bridge Nov. 17-18 during offpeak hours to adjust the height of manhole covers.
  • North bridge sidewalk closed: A section of the north sidewalk of the Sellwood Bridge will be closed from this morning until Nov. 23 (estimated completion) while the contractor uses the sidewalk to do work on the outside of the bridge structure below. Sidewalk users will use ramps to access a protected path that will be separated by a buffer zone from the westbound traffic lane.
  • SE Tacoma and SE 6th Ave.: On Nov. 18 after 9 am, the traffic signal will be turned off and the intersection will be flagged for up to 6 hours while crews install a bicycle box pavement marking and additional striping on 6th Ave.
  • SE Spokane St.: There will be no on-street parking west of SE Oaks Park Way on Nov. 18 after 6 am during paving of the north side of Spokane St. On-street parking will reopen on Nov. 19.

Sellwood Bridge Field Work Notice – November 10, 2016

Trolley tracks have been re-installed north of the bridge

Trolley tracks have been re-installed north of the bridge

Field Work Notice - November 10, 2016

TRAFFIC ALERTS

Much of our remaining work is weather-dependent. Last-minute schedule changes may be required due to heavy rain. Here’s the current schedule:

  • Springwater Trail: The trail is closed between SE Spokane St. and SE Umatilla St. until Nov. 15 for trail repairs and paving, weather permitting. Trail users are being detoured to 6th Ave.  There will be brief delays when the trail is reopened for striping.
  • Hwy. 43 Lane Closure: On Saturday, Nov. 12, a northbound lane will be closed while the contractor removes a sidewalk on the east side of Hwy. 43 south of the Macadam Bay/Freeman Motors driveway. The lane may be closed at other times for this work.
  • Spokane St.: The eastbound lane of SE Spokane St. is closed at times near SE Oaks Park Way during paving work above a stormwater line.
  • East Side Traffic Congestion: There has been an increase in traffic congestion on the east side of the bridge during peak hours.  Tacoma St. and side streets near the bridge are often congested, even when construction is not occurring. The Portland Bureau of Transportation will work with the Sellwood neighborhood association (SMILE) on the traffic issue after bridge construction is completed this fall. The plan is to assess where congestion is occurring after construction is over, so solutions can be considered.
(more)

Sellwood Bridge Field Work Notice – November 4, 2016

Field Work Notice - November 4, 2016, Posted on November 7, 2016

TRAFFIC ALERTS

Much of our remaining work is weather-dependent. Last-minute schedule changes may be  required due to heavy rain. Note: Crews will be working this  Saturday and Sunday (Nov. 5-6) at several areas of the project.  

  • Spokane St.: The eastbound lane of SE Spokane St. is closed at times near SE Oaks Park  Way during work on a stormwater line. A flagger directs traffic when  the lane is closed.
  • Hwy.43: There will be lane closures at times on both sides of the highway to  accommodate final shoulder grading, barrier grouting, curb  and sidewalk replacement, and sign  installation.
  • Springwater Trail:  The trail will be closed from  Umatilla to Spokane beginning Tuesday or Wednesday for repaving for approximately one week, pending  weather.  Flaggers will detour trail users to  6th Ave.
  • East Side Traffic Congestion: There has been an increase in traffic congestion on the east  side of the bridge during peak hours.  Tacoma St. and side  streets near the bridge are often congested, even when  construction is not occurring. The Portland Bureau of  Transportation will work with the Sellwood neighborhood  association (SMILE) on the traffic issue after bridge construction is completed this fall. The  plan is to assess where congestion is occurring after  construction is over, so solutions can be considered.
  • Cemetery access:  As it was prior to the construction of the Sellwood Bridge,  Riverview Cemetery is closing its access in the late afternoons (4 pm) to auto  traffic. The cemetery is private property and the volume and  speed of cars using the cemetery driveway from Taylors Ferry  as a cut through to the bridge has increased.  Cyclists  may still use the cemetery driveway.
(more)

Traffic Alert - Multi-Use Path

November 2, 2016

From 8 pm to midnight on Wednesday, November 2, the Sellwood Bridge contractor will be laying ballast, ties and tracks where the trolley line intersects with the multi-use path. The location is just north of the Sellwood Bridge, in the old Staff Jennings area on the west side of the river.  Please use caution—flaggers will help direct cyclists and pedestrians through the area.


Sellwood Bridge Field Work Notice – October 28, 2016

Laying track for the trolley line south of Freeman Motors

Laying track for the trolley line south of Freeman Motors

Field Work Notice - October 28, 2016

TRAFFIC ALERTS

Much of our remaining work is weather-dependent. Last-minute schedule changes may be required due to heavy rain. Here’s the current schedule:

  • Spokane St.: The eastbound lane of SE Spokane St. is closed at times near SE Oaks Park Way during work on a stormwater line. A flagger directs traffic when the lane is closed.
  • Hwy. 43 Lane Closure: On Saturday, Oct. 29 the southbound lane of Hwy. 43 will be closed north of the bridge while the contractor removes a concrete curb. A new curb will be poured later.
  • East Side Traffic Congestion: There has been an increase in traffic congestion on the east side of the bridge during peak hours.  Tacoma St. and side streets near the bridge are often congested, even when construction is not occurring. The Portland Bureau of Transportation will work with the Sellwood neighborhood association (SMILE) on the traffic issue after bridge construction is completed this fall. The plan is to assess where congestion is occurring after construction is over, so solutions can be considered.
(more)

Sellwood Bridge Field Work Notice – October 21, 2016

The south sidewalk of the bridge is nearly complete.

Field Work Notice - October 21, 2016

TRAFFIC ALERTS

As we enter the rainy season, much of our remaining work is weather-dependent. Last-minute schedule changes may be required. Here’s the current schedule:

  • 6th & Tacoma signal: An infestation of ants caused the signal to malfunction and delay motorists for several days this week. The problem, which was not related to construction, was fixed and the signal is working. The City of Portland has added a westbound left turn phase to improve traffic flow on Tacoma St. Police are citing drivers that make illegal left turns northbound from 6th Ave to the bridge. The City plans more signal changes to improve east/west traffic flow in the next week.
  • Spokane St.: One lane of SE Spokane St. is closed at times for several weeks during work on a stormwater line. A flagger directs traffic when the lane is closed and the trench is covered by a steel plate at night.
  • East Side Traffic Congestion: There has been an increase in traffic congestion on the east side of the bridge during peak hours. Tacoma St. and side streets near the bridge are often congested, even when construction is not occurring. The Portland Bureau of Transportation will work with the Sellwood neighborhood association (SMILE) on the traffic issue after bridge construction is completed. The plan is to assess where congestion is occurring after construction is over, so solutions can be considered. We will share updates on this project.
(more)

Sellwood Bridge Field Work Notice – October 12, 2016

Subgrade along the future westside trolley track

Subgrade along the future westside trolley track

Field Work Notice - October 12, 2016

TRAFFIC ALERTS

As we head into the rainy season, please note that much of our remaining work is weather-dependent. Last-minute schedule changes may be required. Here’s the current schedule:

  • 6th & Tacoma signal: The City of Portland will add a westbound left turn phase to the signal this week. The work will shut down the eastbound left turn for several hours, so drivers will need to turn left at a street to the east temporarily.
  • Spokane St.: One lane of SE Spokane St. will be closed at times for several weeks during construction of a manhole and stormwater line. A flagger will direct traffic during a lane closure tonight. Next week the trench will be covered by a steel plate at night.
(more)

Sellwood Bridge Traffic Alert for October 11-12

Project Alert - October 10, 2016

Drivers who use the Sellwood Bridge or Hwy. 43 near the bridge on October 11 – 12 should expect traffic delays on both days during placement of permanent lane striping. Lane closures will add to traffic delays. The north bridge sidewalk will remain open. The work is weather dependent.

  • Tuesday, October 11, 7 am to 4 pm:  Areas to be striped include SE Tacoma St. west of SE 6th Ave., SW Miles Place, and Hwy. 43 from the project limits south of the bridge to SW Taylors Ferry Road, including the Macadam Bay/Freeman Motors driveway.
  • Wednesday, October 12, 9 am to 4 pm: The Sellwood Bridge. Drivers may want to use alternate routes such as the Ross Island Bridge to avoid delays. 

Sellwood Bridge Field Work Notice – October 7, 2016

Sunday Parkways event on Sellwood Bridge (10/02/16)

Sunday Parkways event on Sellwood Bridge (10/02/16)

Field Work Notice - October 7, 2016

TRAFFIC ALERTS

As we head into the rainy season, please note that much of our remaining work is weather-dependent. Last-minute schedule changes may be required. Here’s the current schedule:

  • Bridge Work Saturday Night: Only one traffic lane will be open at the east end of the bridge Saturday night, Oct. 8, while concrete barriers are moved before striping is placed. Flaggers will direct traffic in both directions, but expect delays.
  • Striping Work:  Weather permitting, permanent lane striping is scheduled on the bridge and Hwy. 43 Sunday afternoon, Oct. 9 and Tuesday night, Oct. 11.  
  • Hwy. 43 Southbound Lane Closure: The outside southbound lane of Hwy. 43 will be closed north of the bridge during offpeak hours on Friday, Oct. 7 and Monday, Oct. 10 while the contractor removes vegetation from the slope on the west side of the highway.
  • 6th & Tacoma signal: A westbound left turn phase will be added to the signal next week. The work will shut down the eastbound left turn for several hours, so drivers will need to turn left at a street to the east temporarily.
  • Spokane St.: On Monday night and Tuesday, Oct. 10-11, one lane of Spokane St. will be closed during construction of a manhole for a stormwater line. Flaggers will direct traffic during the lane closure.
(more)

Sellwood Bridge Field Work Notice – September 30, 2016

Installing rebar for south sidewalk on east aproach

Installing rebar for south sidewalk on east aproach

Field Work Notice - September 30, 2016

TRAFFIC ALERTS

Sellwood Bridge closure Sunday: The bridge will be closed to motor vehicles only from 9 am to 6 pm on Sunday, October 2 during the Sunday Parkways event.  The bridge will be open to bicyclists and pedestrians, including thousands expected to ride the Parkway course through Sellwood and Milwaukie. Stop by our booth at the bridge for a free souvenir Sellwood Bridge button and pin. The alternate river crossings during the closure are the Ross Island and Abernethy (I-205) bridges.

(more)

Sellwood Bridge night work on Hwy. 43 Sept. 28 - 29

Construction Alert - September 28, 2016

Construction work is planned on Highway 43 just south of the Sellwood Bridge on Wednesday and Thursday nights, September 28 - 29 from 7 pm until as late as 6 am. The work will require lane closures, so travelers should expect delays.

  • September 28: The contractor will grind and pave traffic lanes at the south end of the project. Neighbors may notice work lights and hear this night work.
  • September 29: The contractor will close traffic lanes during installation of a large traffic sign over Highway 43.

To report excessive construction noise, call 503-988-4884.


Sellwood Bridge Field Work Notice - September 23, 2016

Goats removing blackberries along trail near Sellwood Bridge.

Goats removing blackberries along trail near Sellwood Bridge.

Field Work Notice - September 23, 2016

TRAFFIC ALERTS

  • Sellwood Bridge closure Sunday: The bridge will be closed to motor vehicles only from 5 am on Sunday, Sept. 25 until no later than 6 am on Monday, Sept. 26 to allow the contractor to seal the deck of the west end of the bridge. The bridge will remain open to bicyclists and pedestrians. If the work cannot be completed Sunday, the bridge may be closed Monday night after 7 pm. An update will be sent out if a Monday night closure is needed.
  • Hwy 43 Night Work Sept. 26-27: Night work is planned on Monday and Tuesday, Sept. 26-27 to grind and repave Hwy. 43 traffic lanes south of the bridge. Drivers should expect delays after 7 pm.
  • Lane striping on Hwy. 43 Sept. 29-30: One lane will be closed in each direction during off-peak hours on Hwy. 43 to replace lane striping at the north and south ends of the project. Expect delays.
  • SE Tacoma/SE 6th Ave. traffic signal: Please note that northbound traffic on SE 6th Ave. can only turn right at the new signal at SE Tacoma St. Police traffic enforcement has been requested because many northbound drivers are making illegal left turns.
(more)

Sellwood Bridge Field Work Notice – September 16, 2016

A herd of goats are clearing blackberries along the eastside river bank

A herd of goats are clearing blackberries along the eastside river bank

Field Work Notice - September 16, 2016

TRAFFIC ALERTS

  • Bridge closure for night work on Hwy. 43 interchange: The deck of the west end of the bridge, above Hwy. 43, will be sealed like the rest of the bridge. This work will be done at night as soon as Sept. 19, weather permitting, with flaggers directing traffic. The work could take three nights to complete. Night time bridge closures may be required on Sept. 22 and 23. The project will send out a field work notice and update the website when the closures are confirmed.
  • Sept. 22 night work on Hwy. 43: Lane closures will be needed Thursday night during installation of a large sign that cantilevers over traffic lanes. The work may be scheduled later, based on the subcontractor’s schedule.
  • Hwy. 43 traffic signal: The Portland Bureau of Transportation is aware of congestion related to the new traffic signal at the west end of the bridge and is making adjustments to improve flow.  Please do not block the intersection for other turn movements after the light turns red.  Portland Transportation staff are studying traffic patterns and will refine the signal timing in the short term and after permanent striping is in place.
  • SE Tacoma/SE 6th Ave. traffic signal: Please note that northbound traffic on SE 6th Ave. can only turn right at the new signal at SE Tacoma St. Police traffic enforcement has been requested because many northbound drivers are making illegal left turns.
(more)

Sellwood Bridge Field Work Notice – September 9, 2016

Field Work Notice - September 9, 2016

TRAFFIC ALERTS

  • Bridge Deck work: The contractor will be closing one lane of the Sellwood Bridge on Saturday night 9/10) and Monday night (9/12) from 7 pm to 6 am (both nights) to seal the bridge deck.  Flaggers will be directing traffic through a single lane.  Consider other travel routes if you need to cross the river during these nights.
  • Bridge Traffic Shift: After the bridge deck is sealed,westbound bridge traffic will be moved north, currently scheduled for Tuesday Sept. 13.  Please be alert when driving through this new traffic stage.  This traffic phase will straighten out the existing curve near the east end of the span.
  • SE Tacoma/SE 6th Ave signal: Traffic on Tacoma is allowed to turn left on to 6th. Northbound traffic on SE 6th Ave. can ONLY turn right onto eastbound SE Tacoma St. now, and ONLY on a green light. Drivers can cross or turn left onto Tacoma from streets east of SE 6th.  There have been a number of vehicles seen going straight through the signal or turning left onto the bridge.  IMPORTANT- Portland police will be monitoring this area and may cite those violating the right turn only.

On-street parking has been removed on the east side of SE 6th Ave. near the signal. Bicyclists and pedestrians northbound on 6th can cross Tacoma and access the bridge by using the pavement loops or signal push buttons.

  • Signal Adjustments:  With the new signal in at the west end of the bridge, there has been some additional congestion on onramps entering the bridge from Hwy 43.  PBOT engineers are making many incremental adjustments to the signals at the west end of the bridge to determine optimal timing to reduce congestion.  Factored in are the impacts to the timing of the signals at the east side of the bridge on Tacoma (at 6th, 13th, and farther east) and the volume of traffic at different days and times. It will take some time to finalize the signal timing for traffic flow through all the signals in the area.  Expect delays during this necessary process and drive with caution.
  • Hwy. 43 interchange: Traffic westbound across the bridge can now turn left at the west end to access Hwy. 43 south. The turnaround loop for southbound traffic at Taylors Ferry Road has closed. 
(more)

Sellwood Bridge Field Work Notice – September 2, 2016

View of interchange from the North

View of interchange from the North

Field Work Notice - September 2, 2016

TRAFFIC ALERTS

New Traffic Signals:

  • Hwy. 43 interchange: Traffic westbound across the bridge can now turn left at the west end to access Hwy. 43 south. The turnaround loop for southbound traffic at Taylors Ferry Road has closed.
  • Signal Adjustments:  With the new signal in at the west end of the bridge, there has been some additional congestion on onramps entering the bridge from Hwy 43.  PBOT engineers are making many incremental adjustments to the signals at the west end of the bridge to determine optimal timing to reduce congestion.  Factored in are the impacts to the timing of the signals at the east side of the bridge on Tacoma (at 6th, 13th, and farther east) and the volume of traffic at different days and times. It will take some time to finalize the signal timing for traffic flow through all the signals in the area.  Expect delays during this necessary process and drive with caution.
  • SE Tacoma/SE 6th Ave signal: Traffic on Tacoma is allowed to turn left on to 6th. Northbound traffic on SE 6th Ave. can ONLY turn right on SE Tacoma St. now, and ONLY on a green light. Drivers can cross or turn left onto Tacoma from streets east of SE 6th.  There have been a number of vehicles seen going straight through the signal or turning left onto the bridge.  IMPORTANT- Portland police will be monitoring this area and may cite those violating the right turn only.

On-street parking has been removed on the east side of SE 6th Ave. near the signal. Bicyclists and pedestrians northbound on 6th can cross Tacoma and access the bridge by using the pavement loops or signal push buttons.

(more)

Sellwood Bridge Field Work Notice – August 26, 2016

Looking south toward west interchange with Sellwood Bridge

Looking south toward west interchange with Sellwood Bridge

Field Work Notice - August 26, 2016

TRAFFIC ALERTS

New Traffic Signals:

  • Hwy. 43 interchange: Traffic westbound across the bridge can now turn left at the west end to access Hwy. 43 south. The turnaround loop for southbound traffic at Taylors Ferry Road has closed. Adjustments are being made to the new traffic signals at the west end of the bridge to improve traffic flow.
  • SE Tacoma/SE 6th Ave:  Northbound traffic on SE 6th Ave. can only turn right on SE Tacoma St. now, and only on a green light. On street parking has been removed on the east side of SE 6th Ave. near the signal. Bicyclists and pedestrians northbound on 6th can cross Tacoma and access the bridge by using the pavement loops or signal push buttons. Drivers can cross or turn left onto Tacoma from streets east of SE 6th.

Westside Trail: Trail users may experience brief delays on Monday, Aug. 29 north of the bridge during some asphalt repair work.

ODOT Ramps Closed Near Ross Island Bridge: Please note that several ramps that connect Hwy. 43 with the Ross Island Bridge/City Center/I-5 south are closed for repairs through Aug. 31. Visit ODOT’s website for information on the ramp closures.

(more)

Sellwood Bridge Field Work Notice – August 19, 2016

New 6th Tacoma traffic signal

New 6th Tacoma traffic signal

Field Work Notice - August 19, 2016

TRAFFIC ALERTS

Aug. 19-23 Bridge Closure: The Sellwood Bridge will be closed to all users from 7 pm on Friday, August 19 until no later than 6 am on Tuesday, August 23. For safety reasons, the bridge sidewalk will also be closed to bicyclists and pedestrians. During the closure crews will remove temporary lane striping, seal the bridge deck, add permanent lane striping, and activate traffic signals at each end of the bridge.  Two major traffic changes will occur when the bridge reopens:

  • Hwy. 43 interchange: Traffic westbound across the bridge will be able to turn left at the west end of the bridge to access Hwy. 43 south. Bridge drivers will no longer need to first travel north to the turnaround at Taylors Ferry Road to travel south.
  • SE Tacoma/SE 6th Ave: The new traffic signal at SE 6th Ave. and SE Tacoma St. will reduce turn movements for northbound traffic on SE 6th, to limit cut-through traffic.  Northbound traffic on 6th must turn right (east) at Tacoma. Bicyclists and pedestrians northbound on 6th can cross Tacoma and access the bridge by using the pavement loops or signal push buttons. Drivers can cross or turn left onto Tacoma from streets east of SE 6th. A new no parking zone will be added to SE 6th Ave. south of Tacoma to accommodate turn movements. See the diagram that shows traffic movements for the new signal.

The alternate routes for motor vehicles during the closure are the Ross Island (north) or Abernethy (south) bridges, via Hwy. 43 or Hwy. 99E. For bicyclists and pedestrians, the alternate routes are the trails on either side of the river north to the Ross Island, Tilikum or Hawthorne bridges.

ODOT Ramps Closed Near Ross Island Bridge: Please note that several ramps that connect Hwy. 43 with the Ross Island Bridge/City Center/I-5 south will be closed during the Aug. 19-23 Sellwood Bridge closure. Work schedules have been adjusted so that the Sellwood Bridge will be closed on only one commute day (Monday, August 22) when the ODOT ramps are closed.  Expect traffic congestion approaching the Ross Island Bridge from the west on August 22. Alternate routes from the Sellwood Bridge to the Ross Island Bridge include Taylors Ferry/Terwilliger or Boundary/Corbett/Hamilton to Barbur to the Ross Island Bridge. Visit ODOT’s website for information on the ramp closures.

Taylors Ferry Turnaround: After the left turn from the Sellwood Bridge to Hwy. 43 opens on Aug. 23, work to remove the temporary turnaround at Taylors Ferry/Hwy. 43 will begin. The turnaround lane is expected to close on Tuesday, Aug. 23.

(more)

Sellwood Bridge Field Work Notice – August 12, 2016

New 6th Tacoma traffic signal

New 6th Tacoma traffic signal

Field Work Notice - August 12, 2016

TRAFFIC ALERTS

Saturday, Aug. 13 Bridge Work: From 5 am to as late as 9 pm traffic will be reduced to one lane on the bridge while the contractor removes the last truss section from the detour bridge. Flaggers will keep traffic flowing in each direction, but bridge users should expect delays.

Aug. 19-23 Bridge Closure: The Sellwood Bridge will be closed to all users from 7 pm on Friday, August 19 until no later than 6 am on Tuesday, August 23. For safety reasons, the bridge sidewalk will also be closed to bicyclists and pedestrians. During the closure crews will seal the bridge deck, remove temporary striping, add permanent lane striping, and activate traffic signals at each end of the bridge.  Two major traffic changes will occur when the bridge reopens:

  • Hwy. 43 interchange: Traffic westbound across the bridge will be able to turn left at the west end of the bridge to access Hwy. 43 south. Bridge drivers will no longer need to first travel north to the turnaround at Taylors Ferry Road to travel south.
  • SE Tacoma/SE 6th Ave: The new traffic signal at SE 6th and SE Tacoma St. will reduce turn movements for northbound traffic on SE 6th, to limit cut-through traffic.  Northbound traffic on 6th must turn right (east) at Tacoma. Bicyclists and pedestrians northbound on 6th can cross Tacoma and access the bridge by using the pavement loops or signal push buttons. Drivers can cross or turn left onto Tacoma from streets east of SE 6th. See the diagram that shows traffic movements for the new signal.

ODOT Ramps Closed Near Ross Island Bridge: Unfortunately, several ramps that connect Hwy. 43 with the Ross Island Bridge/City Center/I-5 south will be closed during the next Sellwood Bridge closure. Work schedules have been adjusted so that the Sellwood Bridge will be closed on only one commute day (Monday, August 22) when the ODOT ramps are closed.  Expect traffic congestion approaching the Ross Island Bridge from the west on August 22. Alternate routes from the Sellwood Bridge to the Ross Island Bridge include Taylors Ferry/Terwilliger or Boundary/Corbett/Hamilton to Barbur to the Ross Island Bridge. Visit ODOT’s website for information on the ramp closures.

(more)

Sellwood Bridge Field Work Notice – August 5, 2016

Entrance to River View Cemetery from bridge after paving

Entrance to River View Cemetery from bridge after paving

Field Work Notice - August 5, 2016

REMAINING WORK

With construction scheduled to end by Thanksgiving 2016, here’s a look at the schedule for remaining work items. All dates are subject to change:

  • Bridge closure for deck sealing, permanent lane striping: Several days in mid-to-late August (dates TBD)
  • Left turn from bridge to Hwy. 43 south opens: August 29
  • Activate traffic signals at west end of bridge and at SE Tacoma/6th Ave.: August 29
  • Traffic lanes and sidewalk on north side of east approach open: August 24
  • In-water work (remove detour bridge, piles, fenders, work bridges) ends: October 31
  • South sidewalk of bridge opens: November 16
(more)

Sellwood Bridge Field Work Notice - July 30, 2016

The Sellwood Bridge will reopen to all traffic modes no later than 7:30 pm tonight, Saturday, July 30.  The bridge has been closed since Thursday morning while the contractor paved the approaches to the bridge and the ramps of the Highway 43 interchange at the west end of the bridge.  A crane was also positioned on the new bridge to lift several sections of the old bridge and set them onto a river barge.  The bridge was originally scheduled to reopen to traffic on Sunday morning, but the contractor was able to complete work ahead of schedule.

Sellwood Bridge Field Work Notice – July 28, 2016

Old Sellwood truss sections and river piles on barges

Old Sellwood truss sections and river piles on barges

Field Work Notice - July 28, 2016

TRAFFIC ALERTS

Bridge Closure: The Sellwood Bridge is closed to all users from 6 am on Thursday, July 28 until no later than 6 am on Sunday, July 31 due to paving and other work.  The Ross Island and I-205 Abernethy bridges are alternate crossings, while bicyclists and pedestrians can use the Tilikum Crossing and Hawthorne bridges. Highway 43 remains open. During the closure, the City of Portland will pave SE Tacoma St. between SE 6th Ave. and SE 17th Ave.

Cemetery Entrance: The entrance to historic River View Cemetery from Highway 43 at the west end of the Sellwood Bridge will be paved the night of July 29. Bicyclists and pedestrians can use the entrance to access the Westside regional trail north of the bridge while the bridge is closed. The entrance is closed to motor vehicles until Monday, August 1. Motor vehicles can enter the cemetery from SW Taylors Ferry Road or SW Boones Ferry Road.

(more)

Sellwood Bridge Field Work Notice – July 15, 2016

Work on cap column for bike-ped bridge under Sellwood Bridge

Work on cap column for bike-ped bridge under Sellwood Bridge

Field Work Notice - July 15, 2016

TRAFFIC ALERTS

July 14 – 17 Bridge Closure: The Sellwood Bridge is closed to motor vehicles only from 6 am on Thursday, July 14 until no later than 6 am on Monday, July 18.  The closure is needed for a concrete pour and cure for the deck of the east approach. Traffic vibrations can damage concrete during the cure. The bridge is open to bicyclists and pedestrians. The Ross Island and I-205 Abernethy bridges are alternate crossings. During the closure, the City of Portland will close a lane of SE Tacoma St. between SE 6th Ave. and SE 17th Ave. to grind asphalt in preparation for a paving project this summer.

Highway 43 Lane Closures: Lanes north of the bridge are closed around the clock while the contractor rebuilds lanes in preparation for final paving. Paving of the lanes and bridge ramps is planned in late July. Night paving (7 pm to 6 am) is planned Thursday, July 21 on the southbound ramp from Hwy. 43 to the bridge and on July 22, 25-27 on Highway 43 north of the bridge.  

Cemetery Entrance Closure: The entrance to historic River View Cemetery from Highway 43 at the west end of the Sellwood Bridge is closed to motor vehicles only until Thursday, July 21, weather permitting, due to construction of a new entrance. The closure will allow the contractor to build curbs, sidewalks and the new driveway, and grade and pave a public parking lot for users of Powers Marine Park. Cemetery users should enter from SW Taylors Ferry Road or SW Boones Ferry Road. The entrance from Highway 43 is open to bicyclists and pedestrians during cemetery business hours.

July 28-31 Bridge Closure: The Sellwood Bridge will be closed to all users for four days to allow the contractor to pave the Tacoma St. approach to the bridge, the westside interchange ramps and the through lanes of Highway 43.  Highway 43 will remain open.

(more)

TRAFFIC ADVISORY: Street improvements on SE Tacoma Street from SE 6th Avenue to SE 17th Avenue, July 14-18

Traffic Advisory from PBOT

PBOT Contact

Dylan Rivera
503-823-3723 
dylan.rivera@portlandoregon.gov

TRAFFIC ADVISORY:
(July 11, 2016) – The City of Portland Bureau of Transportation advises the traveling public that street improvements will require lane closures on SE Tacoma Street from SE 6th Avenue to SE 17th Avenue on Thursday, July 14, through Sunday, July 17, 7 a.m. through 5 p.m. each work day.

The lane closures will allow crews to grind 2.2 lane miles of pavement in preparation for paving at a later date. Both grinding and paving are being coordinated with the Sellwood Bridge closures to alleviate heavy traffic delays.

(more)

Sellwood Bridge Field Work Notice – July 8, 2016

Columns for bicycle-pedestrian bridge rise south of Sellwood Bridge

Columns for bicycle-pedestrian bridge rise south of Sellwood Bridge

Field Work Notice - July 8, 2016

TRAFFIC ALERTS

July 14 – 17 Bridge Closure: The Sellwood Bridge is scheduled to be closed to motor vehicles only from 6 am on Thursday, July 14 until no later than 6 am on Monday, July 18.  The closure is needed during the concrete pour and cure for the seam down the center of the east approach deck. Traffic vibrations can damage concrete during the cure. The bridge will remain open to bicyclists and pedestrians. The Ross Island and I-205 Abernethy bridges are alternate crossings during the closure.

Highway 43 Lane Closures: Lanes north of the bridge are closed at off-peak hours next week during preparation for final paving and other work. This week the contractor removed sidewalk on the east side, placed concrete curbs, and installed conduit for traffic loops on the ramp from southbound Hwy. 43 to the bridge. Next week the contractor will remove the highway median near the old Macadam Bay entrance and grade this area to prepare for final paving in late July.

Westside Trail: The regional trail between the west end of the bridge and SW Miles Place has opened and the old path along the east shoulder of Hwy. 43 between the bridge and Freeman Motors has closed. Trail users need to yield to construction vehicles where the trail crosses the construction road north of the bridge.

(more)

TRAFFIC ALERT: WESTSIDE TRAIL OPENS TUESDAY, JULY 5

Traffic Alert - July 5, 2016

Related articles

Westside regional trail diagram 
Westside regional trail diagram 

Westside regional trail diagrams

The regional trail between the west end of the Sellwood Bridge and SW Miles Place opened Tuesday, July 5. With the opening of this new offroad trail, the old path along the east shoulder of Highway 43 between the bridge and Freeman Motors will close. The contractor will remove the sidewalk south of Freeman Motors and construct a new curb.

Users of the new trail will need to yield to construction vehicles where the trail crosses the construction road just north of the bridge. There is also four-way stop where the trail intersects with the Macadam Bay driveway.

The trail leads to SW Miles Place, where it connects with a section through Willamette Park to the north. Please use caution on SW Miles Place where the trail alignment follows a residential street. The trail is open in Willamette Park during a current Portland Water Bureau construction project, except for a section that will eventually connect with SW Nevada Street. The regional trail leads north to downtown Portland.

Download two diagrams that show the new section of trail in more detail.


Sellwood Bridge Field Work Notice for July 1

Pit for westside bioswale, with excavated boulders

Field Work Notice - July 1, 2016

TRAFFIC ALERTS

  • Highway 43 Lane Closures: Lanes north of the bridge will be closed at off-peak hours July 5-8 during demolition of the northbound sidewalk, placement of concrete curbs, and installation of conduit for traffic loops on the ramp from southbound Hwy. 43 to the bridge.
  • Westside Trail: The regional trail between the west end of the bridge and SW Miles Place is tentatively scheduled to open by noon on Tuesday, July 5. Watch for a news alert to confirm the trail has opened. The current path along the east shoulder of Hwy. 43 between the bridge and Freeman Motors will be closed to bicyclists and pedestrians after the trail opens. The sidewalk in this area will be removed permanently. Trail users need to yield to construction vehicles where the trail crosses the construction road north of the bridge. There is a four-way stop where the trail intersects with the Macadam Bay driveway.
  • July 14 – 17 Bridge Closure: The Sellwood Bridge is scheduled to be closed to motor vehicles only from 6 am on Thursday, July 14 until no later than 6 am on Monday, July 18. The closure is needed during the concrete pour and cure for the seam of the east approach deck that borders the south half of the approach. Traffic vibrations can damage concrete during the cure. The bridge will remain open to bicyclists and pedestrians.
(more)

Sellwood Bridge Field Work Notice – June 24, 2016

West truss span being lowered by hydraulic jacks

West truss span being lowered by hydraulic jacks

Field Work Notice – June 24, 2016

TRAFFIC ALERTS 

July 14 – 17 Bridge Closure: The Sellwood Bridge is scheduled to be closed to motor vehicles only from 6 am on Thursday, July 14 until no later than 6 am on Monday, July 18.  The closure is needed during the concrete pour and cure for the seam of the east approach deck that connects to the south half of the approach. Traffic vibrations can damage concrete during the cure. The bridge will remain open to bicyclists and pedestrians.

Cemetery Entrance: The cemetery entrance from Hwy. 43 has shifted south to allow construction on the north side. Cemetery access for motor vehicles, bicyclists, and pedestrians is maintained during cemetery opening hours.

(more)

Sellwood Bridge Field Work Notice – June 17, 2016

South ramp from Hwy 43 to bridge has shifted east

South ramp from Hwy 43 to bridge has shifted east

Field Work Notice - June 17, 2016

TRAFFIC ALERTS

Westside Trail: The opening of the regional trail between the west end of the bridge and SW Miles Place is postponed for two to four weeks while the contractor completes work along the trail. Until the trail opens, bicyclists and pedestrians will continue to use the detour path along the east side of Hwy. 43.

Hwy. 43 Through Lanes:  The lanes under the bridge will be shifted west on Monday, June 20 to allow the contractor to work on the ramp from the bridge to northbound Hwy. 43.

Cemetery Entrance: The stop sign for traffic exiting the cemetery has shifted east toward the bridge. The cemetery entrance from Hwy. 43 will be shifted south as early as June 21. Access for motor vehicles, bicyclists, and pedestrians will be maintained.

(more)

Westside Trail to open within four weeks

Construction Notice - June 14, 2016

The westside regional trail between the Sellwood Bridge and SW Miles Place will be opening within the next four weeks. It was previously announced that the trail would open on June 14 but an inspection revealed additional clean up work needing to be done on and near the trail. To ensure safety for the public and workers, the trail will remain closed during this work. The trail detour route along the east side of Highway 43/Macadam remains open during while work is completed. 


Sellwood Bridge Field Work Notice – June 10, 2016

East Sellwood Bridge truss span on barge

Field Work Notice - June 10, 2016

TRAFFIC ALERTS

Westside Trail: The regional trail between the west end of the bridge and SW Miles Place opens on Tuesday, June 14. The current path along the east shoulder of Hwy. 43 between the bridge and Freeman Motors will be closed to bicyclists and pedestrians after the trail opens, due to construction. The sidewalk in this area will be removed permanently. Trail users need to yield to construction vehicles where the trail crosses the construction road north of the bridge. There is a four-way stop where the trail intersects with the Macadam Bay driveway.

(more)

Sellwood Bridge Field Work Notice - May 27, 2016

Girders were trucked to the bridge and hoisted by two cranes- web

Girders were trucked to the bridge and hoisted by two cranes- web

Field Work Notice - May 27, 2016

This will likely be the last field work notice until the week of June 13 due to staff schedules.

TRAFFIC ALERTS

Highway 43: Along Highway 43 north and south of the bridge, concrete will be poured next week for the foundations of permanent traffic signs. Outside traffic lanes will be closed during some non-peak hours for the concrete pours.

(more)

Sellwood Bridge Field Work Notice for May 19

Concrete river pier columns painted to match steel arches

Concrete river pier columns painted to match steel arches

Field Work Notice - May 19, 2016

Related articles

TRAFFIC ALERTS

Friday, May 20 Bridge Closure: The Sellwood Bridge will be closed to all users from 6 am on Friday, May 20 until as late as 6 am on Saturday, May 21 during installation of concrete girders for the north half of the east approach. The Ross Island and Abernethy (I-205) bridges are the nearest alternate routes. A news alert will be sent out as soon as the bridge reopens.

(more)

Sellwood Bridge Field Work Notice for May 12

Removing deck from west work bridge

Removing deck from west work bridge

Field Work Notice - May 12, 2016

TRAFFIC ALERTS

Hwy. 43 northbound through lane opens:  The northbound through lane of Hwy. 43 has opened on the lower level of the interchange.  Both through lanes are now open, eliminating the need for through traffic to pass the traffic signal on the upper level.

Friday, May 20 Bridge Closure: A bridge closure is planned from 6 am on Friday, May 20 until as late as 6 am on Saturday, May 21 to allow the contractor to install pre-stressed concrete girders for the north half of the east approach. The closure will impact motor vehicles, bicyclists and pedestrians.

(more)

Sellwood Bridge Field Work Notice for May 5

New Sellwood Bridge with old bridge beyond

New Sellwood Bridge with old bridge beyond

Field Work Notice - May 5, 2016

TRAFFIC ALERTS

  • Second Hwy. 43 through lane opens:  On Monday, May 9 the northbound through lane of Hwy. 43 will open, carrying traffic on the lower level of the interchange. Technically, the new lane will be used by southbound traffic, because southbound traffic has been using the northbound lane in recent months.  On Monday, both through lanes will be open for the first time, which will help reduce congestion on the upper level of the interchange. Expect delays during the traffic change from 9 am to 4 pm.
  • May 20 Bridge Closure: A bridge closure is planned from 6 am on Friday, May 20 until as late as 6 am on Saturday, May 21 to allow the contractor to install pre-stressed concrete girders for the north half of the east approach. The closure will impact motor vehicles, bicyclists and pedestrians.
(more)

Sellwood Bridge Field Work Notice for April 29

The caps of the river pier bents are being stained orange-brown

The caps of the river pier bents are being stained orange-brown

Field Work Notice - April 29, 2016

TRAFFIC ALERTS

May 20 Bridge Closure: A bridge closure is planned from 6 am on Friday, May 20 until as late as 6 am on Saturday, May 21 to allow the contractor to install pre-stressed concrete girders for the north half of the east approach. The closure will impact motor vehicles, bicyclists and pedestrians.

(more)

Sellwood Bridge Field Work Notice for April 20

Grading southbound Hwy 43 through lane under bridge

Field Work Notice - April 20, 2016

WEST SIDE WORK

New Bridge and Interchange: In the interchange at the west end of the bridge, concrete was poured this week for the south half of the end panel, where the bridge transitions to land. The parapet wall on the south side of the interchange bridge will be poured this week. The outside girders of the interchange bridge will be stained next week.

Work continues on the two westside interchange ramps. On the southbound ramp from the bridge to Hwy. 43 concrete moment slabs and concrete barrier are being poured. Base paving for the ramp is scheduled late next week. On the north ramp that carries southbound traffic to the bridge, crews are also building a moment slab and overhang and installing conduit for lighting.

(more)

Traffic Alert: Sellwood Bridge has reopened to traffic 4/16

Field Work Update - April 16, 2016

Related articles

The Sellwood Bridge reopened to traffic ahead of schedule today at 4:20 pm. The bridge closed this morning so a contractor could set up two cranes on the deck and lower concrete forms that were used to build the deck. The bridge was scheduled to open by Monday, April 18.


Sellwood Bridge Field Work Notice for April 15

Old Sellwood Bridge with concrete removed from deck

Old Sellwood Bridge with concrete removed from deck

Field Work Notice - April 15, 2016

TRAFFIC ALERTS

  • The Sellwood Bridge will be closed to motor vehicles only from 7 am on Saturday, April 16 to no later than 6 am on Monday, April 18 for construction work. The bridge will remain open to bicyclists and pedestrians, with short delays at times. The closure will allow the contractor to set up two cranes on the bridge deck that will lower falsework from the underside of the deck.
(more)

Sellwood Bridge Field Work Notice for April 8

Installing concrete forms for face of Hwy 43 ramp wall

Installing concrete forms for face of Hwy 43 ramp wall

Field Work Notice - April 8, 2016

TRAFFIC ALERTS

  • The Sellwood Bridge will be closed to motor vehicles only from 7 am on Saturday, April 16 to no later than 6 am on Monday, April 18 for construction work. The bridge will remain open to bicyclists and pedestrians, with short delays at times. The closure will allow the contractor to set up two cranes on the bridge deck that will lower falsework from the underside of the deck.
  • From April 18 – 25, Hwy. 43 will be reduced to one lane in each direction north of the bridge to allow the contractor to remove the median and do grading and paving in preparation for the second through lane under the bridge. The inside lanes need to be closed around the clock during this work.
(more)

Sellwood Bridge Field Work Notice for April 1

Field Work Notice - April 1, 2016

TRAFFIC ALERTS

  • The Sellwood Bridge will be closed to motor vehicles only from 7 am on Saturday, April 16 to no later than 6 am on Monday, April 18 for construction work. The bridge will remain open to bicyclists and pedestrians, with short delays at times. The closure will allow the contractor to set up two cranes on the bridge deck that will lower falsework from the underside of the deck.
  • An outside lane of Hwy. 43 is sometimes closed north of the bridge during off peak hours on weekdays.
(more)

Sellwood Bridge Field Work Notice for March 25

Removing railings of old Sellwood Bridge

Removing railings of old Sellwood Bridge

Field Work Notice - March 25, 2016

TRAFFIC ALERTS 

  • After 9 am on Wednesday, March 30, the contractor will shift the southbound traffic lane from Hwy. 43 at the west end of the bridge to begin a new construction phase. This is a relatively minor change but traffic delays are expected for several hours during the shift.
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
(more)

Sellwood Bridge Field Work Notice for March 18

Concrete deck and railings removed from east end of old bridge

Concrete deck and railings removed from east end of old bridge

Field Work Notice - March 18, 2016

TRAFFIC ALERTS

  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
(more)

Sellwood Bridge Field Work Notice for March 11

Inspecting truss of detour bridge before removing deck

Inspecting truss of detour bridge before removing deck

Field Work Notice - March 11, 2016

BRIDGE OPENING VIDEOS

If you missed the farewell candlelight walk on February 25 for the old bridge or the opening celebration for the new bridge on February 27, check out the links in this section to watch videos of the events.

TRAFFIC ALERTS

The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.

(more)

Sellwood Bridge Field Work Notice for March 4

Anna Kafoury cuts ribbon to open the new Sellwood Bridge

Anna Kafoury cuts ribbon to open the new Sellwood Bridge

Field Work Notice - March 4, 2016

BRIDGE OPENING

The last week was very eventful for the project.  Several thousand fans of the old bridge turned out for a farewell candlelight walk on February 25, the night it closed forever.  Two days later an estimated 10,000 people turned out to celebrate the opening of the new bridge.  On February 29, the bridge actually opened to traffic. The first morning it was open, a woman drove her pickup truck westbound on the six-foot wide temporary path for bicyclists and pedestrians until it was stopped by the concrete barrier.  It was a strange first day for Portland’s newest Willamette River bridge.  

TRAFFIC ALERTS

  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
(more)

New Sellwood Bridge opens to traffic February 29 at 8 p.m.

Posted March 1, 2016

Related articles

The new Sellwood Bridge opens to traffic Monday, February 29 at 8 p.m.  The old bridge closed on February 25 so that the contractor could remove the jump span that connected it to the new bridge and prepare the new bridge for traffic. The contractor was able to reopen the bridge 10 hours ahead of schedule.

(more)

Careless driver mars Sellwood Bridge's opening day

Stuck truck on Sellwood Bridge multiuse path 3-1-2016

Stuck truck on Sellwood Bridge multiuse path 3-1-2016

Project Update - March 1, 2016

It was a rough first morning for the new Sellwood Bridge on March 1.  A careless driver drove a Toyota pickup truck onto the bridge's only path for bicyclists and pedestrians.  After driving several hundred feet westbound down the narrow six-foot wide path, the driver wedged the truck between the concrete barrier and steel railing, completely blocking the path.  Fortunately, no one was injured.  The driver left the scene. The construction team had to remove sections of barrier and pick up the truck with a forklift.  Traffic was flowing again by 8 am.  The driver had to drive up onto the sidewalk from the road, so this was not a case of someone misreading a traffic sign.

(more)

Sellwood Bridge Field Work Notice for February 25

Loading falsework from below new deck onto barge

Loading falsework from below new deck onto barge

Field Work Update - Posted February 25, 2016

BRIDGE OPENING EVENTS

Two big bridge events this week:

  • Thursday, February 25 from 7:30 – 8:30 pm, a farewell candlelight walk will allow fans of the old Sellwood Bridge to cross the 90-year span one last time before it closes forever. The bridge will be closed to motor vehicles during the walk, which will be led by a local bagpiper.  Sellwood resident and former Oregon Governor Barbara Roberts will say a few words of tribute before the walk.  Meet at the east end of the bridge at SE Grand Ave. Access is also open from the Westside trail. Bring your flashlight, phone light, or electric candle to help say farewell to an old span that will close forever tonight.
  • Saturday, February 27 from noon to 4 pm, a community celebration will be held to dedicate the new bridge. Dedication speeches begin at 1 pm, followed by a ribbon cutting, Parade of the Decades, and a water cannon salute from the Portland Fire Bureau’s boat. Enjoy live music, food vendors, and booths from local businesses, non-profits, and public agencies. For event details, visit the project website.

TRAFFIC ALERTS

  • The detour bridge will close to all traffic (including bicyclists and pedestrians) on Thursday, February 25 at 7 pm. The closure will allow the contractor to dismantle the jump span between the bridges, demolish part of the east approach, set up the next traffic stage, and complete other tasks.  The contractor will work around the clock during the closure to get the new bridge ready to open. The Ross Island Bridge and the Abernethy Bridge (I-205) will be the main alternate routes.  Bicyclists and pedestrians may prefer the Hawthorne Bridge as an alternate. The new bridge will open to traffic the first week of March. Watch for an email update for the reopening date and time.
(more)

Sellwood Bridge Field Work Notice for February 19

Hwy 43 interchange with bridge

Hwy 43 interchange with bridge

Field Work Notice - February 19, 2016

BRIDGE OPENING EVENTS

It’s countdown week for some big project events. 

  • On Thursday, February 25 from 7:30 – 8:30 pm, a farewell candlelight walk will allow fans of the old Sellwood Bridge to cross the 90-year span one last time before it closes forever. The bridge will be closed to motor vehicles during the walk, which will be led by a local bagpiper.  Sellwood resident and former Oregon Governor Barbara Roberts will say a few words of tribute before the walk.  Meet at the east end of the bridge at SE Grand Ave. Bring your flashlight, phone light, or electric candle to help say farewell to an old span that will not be with us much longer.
  • On Saturday, February 27 from noon to 4 pm, a community celebration will be held to dedicate the new bridge. Dedication speeches begin at 1 pm, followed by a ribbon cutting, Parade of the Decades, and a water cannon salute from the Portland Fire Bureau’s boat. Enjoy live music, food vendors, and booths from local businesses, non-profits, and public agencies. For event details, visit the project website.

TRAFFIC ALERTS

  • The new bridge will open to traffic on Tuesday, March 1 by 6 am. The detour bridge will close to all traffic for five days beginning Thursday, February 25 at 7 pm. The closure will allow the contractor to dismantle the jump span between the bridges and set up the next traffic stage.   The Ross Island Bridge and the Abernethy Bridge (I-205) will be the main alternate routes during the closure.
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
(more)

Will Sunday Parkways 2016 pass your street? New Milwaukie/Sellwood bike route rolls out

By Dillon Pilorget, The Oregonian - February 17, 2016

There are few feelings like biking down a car-free street, surrounded only by a mob of other cyclists and the occasional walker or skateboarder. That feeling is what Portland's free Sunday Parkways rides are all about, and this year's lineup of five easy-going rides will offer it up on a brand new route through Sellwood and Milwaukie.

Sunday Parkways rides get rolling May 15 in East Portland, closing out Oct. 2 with the new Sellwood/Milwaukie route. The loop routes travel about eight miles through different Portland neighborhoods and past parks, where everything from Zumba classes to bike obstacle courses await next to ice cream trucks and bike repair stations.

This year's new route replaces one that last year traveled north through Sellwood to then just-opened Tilikum Crossing. Much in that style, the Sellwood/Milwaukie route will pass over the new Sellwood Bridge, which is set to open March 1.

Read the full story on OregonLive.com


Sellwood Bridge Field Work Notice for February 12

Concrete poured to lock in steel expansion deck joint

Concrete poured to lock in steel expansion deck joint

Field Work Notice - February 12, 2016

BRIDGE OPENING EVENTS

Join us at two free events later this month that will mark major project milestones.  On Saturday, February 27 from noon to 4 pm, a community celebration will be held to dedicate the new bridge. On Thursday, February 25 from 7:30 – 8:30 pm, a farewell candlelight walk will cross the old bridge one last time before it closes forever. The bridge will be closed to motor vehicles during the walk. For event details, visit the project website.

(more)

Sellwood Bridge Field Work Notice for February 5

Excavating for southbound Hwy 43 ramp to bridge

Excavating for southbound Hwy 43 ramp to bridge

Field Work Notice - February 5, 2016

TRAFFIC ALERTS

  • The new bridge is scheduled to open to traffic on Tuesday, March 1 by 6 am. The detour bridge will close to all traffic (motor vehicles, bicyclists and pedestrians) for four days beginning Thursday, February 25 at 7 pm. The closure will allow the contractor to dismantle the jump span between the bridges and set up the next traffic stage.   
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
(more)

Sellwood Bridge Field Work Notice for January 28

Handrail installed on north parapet wall

Handrail installed on north parapet wall

Field Work Notice - January 28, 2016

TRAFFIC ALERTS

  • This week the southbound Hwy. 43 onramp to the Sellwood Bridge was shifted west. The shift allows the contractor to build the east half of the ramp and the second through lane under the bridge. Be alert for construction work in this area.
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
  • The new bridge is scheduled to open to traffic on Tuesday, March 1 by 6 am. The detour bridge will close to all traffic (motor vehicles, bicyclists and pedestrians) for four days beginning Thursday, February 25 at 7 pm. The closure will allow the contractor to dismantle the jump span between the bridges and set up the next traffic stage.   
(more)

Sellwood Bridge Field Work Notice for January 22

Pouring concrete for north parapet wall

Pouring concrete for north parapet wall

Field Work Notice - posted January 23, 2016

TRAFFIC ALERTS

  • On Monday, January 25 the contractor will shift southbound traffic approaching the bridge west against the retaining wall. This will allow the contractor to build the east half of the ramp and the second through lane under the bridge.  Expect southbound traffic delays on Monday before 4 pm during the traffic change.
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
(more)

Sellwood Bridge Field Work Notice for January 14

Creating construction entrance at east end of bridge

Creating construction entrance at east end of bridge

Field Work Notice - January 14, 2016

BRIDGE OPENING DATE

The contractor plans to open the new bridge to traffic on Tuesday, March 1 by 6 am. The detour bridge will close to all traffic for four days beginning on Thursday, February 25 starting at 7 pm. The closure will allow the contractor to dismantle the jump span between the bridges and set up the next traffic stage. 

A community celebration is planned on the new bridge from noon to 4 pm on Saturday, February 27. All are invited.  More event details will be announced in the next few weeks.

TRAFFIC ALERTS

  • A Highway 43 traffic change is tentatively scheduled for Monday, January 25 (weather permitting).  On that day southbound traffic approaching the bridge from the north will be shifted west against the retaining wall. This will allow the contractor to build the east half of the ramp and the second through lane under the bridge.
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
  • The west-side detour for bicyclists and pedestrians extends north along the east shoulder or sidewalk of SW Macadam St. to SW Nebraska St., due to construction for an unrelated Water Bureau project in Willamette Park.
(more)

Sellwood Bridge Field Work Notice for January 7

New Sellwood Bridge view from the south

TRAFFIC ALERTS

  • A construction entrance has been added at the east end of the bridge. Barricades and traffic control devices can be moved when trucks enter the work zone. This is a construction entrance only, so be cautious of construction vehicles entering and exiting on the bridge.
  • The outside southbound lane of Hwy. 43 is sometimes closed north of the bridge between 7 am and 4 pm on weekdays.
  • The outside northbound lane of Hwy. 43 will be closed north of the bridge on Friday, January 8 from 9 am to 4 pm for a concrete pour.
  • On Wednesday January 13, a southbound lane of Hwy 43 north of the Miles Place/Taylors Ferry intersection will be closed from 9 am to 4 pm for storm drain work.
  • The westside detour for bicyclists and pedestrians extends north along the east shoulder or sidewalk of SW Macadam St. to SW Nebraska St., due to construction for an unrelated Water Bureau project in Willamette Park.
(more)

Browse previous entries: