Field Work and Construction Updates

Updated January 27, 2017: With major construction work now complete, there will no longer be a weekly Field Work Notice. Notices will be posted in 2017 if important field work is scheduled.

Sellwood Bridge Field Work Notice for Dec. 30

Ramp column for west interchange

TRAFFIC ALERTS

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. and this Saturday, Jan. 3 between SW Taylors Ferry Road and the bridge while the contractor works on the west side of traffic lanes. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. south of the bridge during earthwork and storm drain installation.

(more)

East approach construction phases

East approach

The east approach to the Sellwood Bridge is being built in phases.

  • The contractor first built the south half of the east approach and shifted traffic onto that structure in November 2014 (see Traffic Rerouted image).
  • In December, a subcontractor demolished the easternmost spans of the old approach (see Old Bridge Removal image).
(more)

Sellwood Bridge Field Work Notice for Dec. 19

Profile of barge with segments for first 2 steel arch spans downtown 12-15-2014

TRAFFIC ALERTS

Springwater Trail Reopens: The Springwater Trail under the Sellwood Bridge reopened this afternoon following demolition work above the trail. With the old east bridge approach removed, the contractor will begin drilling foundation shafts for the new approach in January, working generally from west to east.

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. south of the bridge during earthwork and storm drain installation. On Saturday, Dec. 20 the outside southbound lane will be closed from 7 a.m. until about 3 p.m.

(more)

First steel arrives for new Sellwood Bridge arch spans

Barge carries segments for first 2 steel arch spans through downtown 12-15-2014

Monday, December 18 marked a major milestone in the construction of the new Sellwood Bridge. A barge arrived carrying the first two steel arches for the western river span.

The arches were fabricated at Thompson Metal Fab in Vancouver, WA. The plate steel was made at a mill in the Eastern US, then shipped by train to Thompson’s plant on the Columbia River. Workers at Thompson cut, welded and bolted the steel into full length arches, and then dismantled the arches into shorter segments for shipping and erection.

(more)

Sellwood Bridge Field Work Notice for Dec. 12

Demolition of old east approach

TRAFFIC ALERTS

Springwater Trail Closure: A short section of the Springwater Trail under the Sellwood Bridge remains closed until the afternoon of December 19 due to demolition of the old east bridge approach.  Work next week involves a section of the old abutment. The trail is closed between SE Spokane Street and SE Umatilla Street. The detour uses SE 7th Street to cross SE Tacoma Street and rejoin the trail. 

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during earthwork and storm drain installation.

(more)

Sellwood Bridge Field Work Notice for Dec. 12

Old bridge dedication plaque salvaged

TRAFFIC ALERTS

Springwater Trail Closure: A short section of the Springwater Trail under the Sellwood Bridge remains closed until the afternoon of December 19 due to demolition of the old east bridge approach. Work next week involves a section of the old abutment. The trail is closed between SE Spokane Street and SE Umatilla Street. The detour uses SE 7th Street to cross SE Tacoma Street and rejoin the trail.

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during earthwork and storm drain installation.

(more)

Sellwood Bridge Field Work Notice for Dec. 5

Demolition of old east approach

TRAFFIC ALERTS

Springwater Trail Closure: A short section of the Springwater Trail under the Sellwood Bridge will be closed December 8 - 19 during demolition of the old east approach to the bridge.  The closed section is between SE Spokane Street and SE Umatilla Street. Trail users will be directed to a detour on SE 7th Avenue to cross SE Tacoma Street and rejoin the trail. 

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during earthwork and storm drain installation. 

Night Work on Hwy. 43:  Three lanes continue to be closed on Hwy. 43 on weeknights through December 12, from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls.  Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work Notice for Dec. 5

Field Work Update - December 5, 2014

TRAFFIC ALERTS

Springwater Trail Closure: A short section of the Springwater Trail under the Sellwood Bridge will be closed December 8 - 19 during demolition of the old east approach to the bridge. The closed section is between SE Spokane Street and SE Umatilla Street. Trail users will be directed to a detour on SE 7th Avenue to cross SE Tacoma Street and rejoin the trail.

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during earthwork and storm drain installation.

Night Work on Hwy. 43: Three lanes continue to be closed on Hwy. 43 on weeknights through December 12, from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls. Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work Notice for Nov. 24

Workers setting forms for Bent 5 column

Field Work Update - November 24, 2014

Due to the Thanksgiving Holiday this will be the only field work notice this week. The contractor does not plan to work Nov. 27 – 30 during the Thanksgiving holiday, although staff may visit to check concrete cures.

Bridge Closure Completed: The project team thanks bridge users for the patience during last week’s three-day bridge closure. The bridge opened ahead of schedule at 7:20 p.m. on Friday, with traffic using the new east approach (see photo). Due to the greater curve in the east approach, the advisory speed limit was lowered from 25 mph. to 20 mph. The staircase from the bridge sidewalk to the Springwater Trail and access to the bridge sidewalk from SE Grand Ave. have closed, due to construction on the old east approach.

TRAFFIC ALERTS

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.

Night Work on Hwy. 43: Three lanes will continue to be closed on Hwy. 43 on weeknights through Dec. 5 from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls. Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge opens at 8 p.m. Friday night

Field Work Update -November 21, 2014

Related articles

The Sellwood Bridge will reopen at 8 p.m. Friday, November 21 after a three-day closure to shift traffic onto the new east approach. The speed limit on the bridge has been lowered from 25 m.p.h. to 20 m.p.h. due to the longer curve at the east end of the bridge. Please note that the bridge is limited to vehicles weighing up to 10 tons and 30 feet in length.

The project team thanks the community for their patience during this bridge closure. The bridge will remain open through the rest of the year, so please remember to support local businesses during the holidays.


Bridge To Reopen After Evening Commute, November 21

Field Work Update

Related articles

The Sellwood Bridge is closed to all traffic modes from 5 a.m. on Wednesday, November 19 until sometime after the evening commute Friday, November 21. At the latest, the bridge will reopen by midnight on Friday. The bridge was closed to set up a traffic control change to the east approach.  When the bridge reopens, traffic will use the new east approach. Hwy. 43 will remain open.


Sellwood Bridge Field Work Notice for Nov. 14

Installing barrier on east approach

Installing barrier on east approach

Field Work Update - November 14, 2014

TRAFFIC ALERTS

Bridge Closure Nov. 19 - 21: The Sellwood Bridge will be closed to all traffic from 5 a.m. on Wednesday, Nov. 19 until as late as 11:59 p.m. on Friday, Nov. 21 to shift traffic onto the new east approach (on the south side of Tacoma). The bridge sidewalk will also be closed. The Ross Island Bridge is the alternate route for northbound traffic and the Hawthorne Bridge is an alternate route for bicyclists. The traffic switch will allow work on the north half of the new east approach to begin in 2015.  We encourage drivers to plan for an alternate route now before the closure

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Night Work on Hwy. 43:  Three lanes will continue to be closed on Hwy. 43 on weeknights from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls.  Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work notice for November 7

Span 8 Form Removed

Span 8 Form Removed

Field Work Update - November 7, 2014

TRAFFIC ALERTS

Bridge Closure November 19: The Sellwood Bridge will be closed to all traffic from 5 a.m. (new time) on Wednesday, Nov. 19 until as late as 11:59 on Friday, Nov. 21 to shift traffic onto the new east approach (on the south side of Tacoma). The bridge sidewalk will also be closed, but may be able to re-open early on Friday. The traffic switch will allow work on the north half of the new east approach to begin in 2015.  We encourage drivers to plan for an alternate route now before the closure.

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Saturday lane closures:  On Saturdays the contractor will close lanes on Hwy. 43 north of the bridge during drilling for tie-back anchors for the west retaining walls. One lane will remain open in each direction during the work.

Night Work on Hwy. 43:  Three lanes will continue to be closed on Hwy. 43 on weeknights from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls.  Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work Notice for Oct. 31

Rebar mats on west approach deck

Rebar mats on west approach deck

Field Work Update - October 31, 2014

TRAFFIC ALERTS

Bridge Closure: A bridge closure is planned from 7 p.m. on Wednesday, Nov. 19 until as late as 11:59 p.m. on Friday, Nov. 21 to shift traffic onto the new east approach. The bridge sidewalk will also be closed, but may be able to re-open early on Friday. The traffic switch will allow work on the north half of the new east approach to begin in 2015.

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Saturday lane closures:  On Saturdays for the next several weeks the contractor will close lanes on Hwy. 43 north of the bridge during drilling for tie-back anchors for the west retaining walls. One lane will remain open in each direction during the work.

Night Work on Hwy. 43:  Three lanes will also be closed on Hwy. 43 on weeknights into the second week of November from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls.  Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work Notice for Oct. 24

Bent 4 column forms

Bent 4 column forms

Field Work Update - October 24, 2014

TRAFFIC ALERTS

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Saturday lane closures:  On Saturdays through October the contractor will close lanes on Hwy. 43 north of the bridge during drilling for tie-back anchors for the west retaining walls. One lane will remain open in each direction during the work.

Night Work on Hwy. 43:  Three lanes will also be closed on Hwy. 43 on weeknights from Oct. 27 – Nov. 7 from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls.  Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work Notice for Oct. 16

Concrete pour at east river pier, wide

Concrete pour at east river pier, wide

Field Work Update - October 16, 2014

TRAFFIC ALERTS

Hwy. 43 lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Saturday lane closures:  During the day on Saturday, Oct. 18 the contractor will close lanes on Hwy. 43 north of the bridge during drilling for tie-back anchors for the west retaining walls. One lane will remain open in each direction during the work.

Night Work on Hwy. 43:  Three lanes will also be closed on Hwy. 43 on weeknights, as early as Oct. 20 through 30 from 7 p.m. to 6 a.m. during installation of a new storm drain system at the base of the west side retaining walls.  Flaggers will direct traffic on a single open lane.

(more)

Sellwood Bridge Field Work Notice for Oct. 10

East Tacoma Paving

East Tacoma Paving

Field Work Update - October 10, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

New Waterline: This week the contractor will be excavating the east side of Hwy 43 in preparation for round the clock installation of a new waterline the following week. Traffic will be shifted slightly to the west.

Sellwood Bridge delays:  Motorists should expect delays on the Sellwood Bridge as concrete trucks access Tacoma and Spokane streets from 6 a.m. October 16 through early evening October 17 for a 36 hour continuous concrete pour for Bent 5.  The public is encouraged to find alternate routes during this time period.

Weekend work: Crews will be working next few Saturdays on the NW retaining walls.  Double lane closures will be necessary.  Please use caution when traveling through the area.

(more)

Sellwood Bridge construction traffic alert for Oct. 8

Related articles

Sellwood Bridge construction is expected to impact traffic on the bridge and SE Tacoma St. on Wednesday, Oct. 8, from 9 a.m. until as late as 3 p.m. One of the two traffic lanes will be closed at the east end of the bridge while crews complete the repair of an expansion joint in the deck. (This work was re-scheduled for Oct. 8.) Flaggers will direct two-way traffic on the open lane. Additional truck traffic is also expected on Wednesday at the east end of the bridge, due to paving work on the new east approach. Travelers can avoid delays by using alternate routes such as the Ross Island Bridge.


Sellwood Bridge Field Work Update for October 3

Bird's eye view of west river pier concrete pour

Bird's eye view of west river pier concrete pour

Field Work Update - October 3, 2014

TRAFFIC ALERTS

Bridge Lane Closures Oct. 6 – 7:  One lane will be closed near the east end of the bridge on Monday and Tuesday from 9 a.m. until as late as 4 p.m. while crews replace an expansion joint in the bridge deck. Flaggers will direct two-way traffic in the open lane.  This work will slow traffic, so bridge users should consider using alternate routes to avoid delays.

Tacoma Paving on Oct. 8:  The closed south side of Tacoma is scheduled to be paved on Wednesday, Oct. 8 between SE 6th Ave. and the bridge.  This work will increase truck traffic near the east end of the bridge.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.  On weekdays through Oct. 7 a third party contractor is installing a fiber optic line under a closed traffic lane south of the bridge (from 9 a.m. to 3 p.m.).

(more)

Sellwood Bridge Field Work Update for September 26

Close-up of 300,000 lb concrete piece

Close-up of 300,000 lb concrete piece

Field Work Update - September 26, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds west side retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.  On weekdays through Oct. 3 a third party contractor is installing a fiber optic line under a closed traffic lane south of the bridge (from 9 a.m. to 3 p.m.).

Tacoma Street:  Reminder - Construction of the south side of the new bridge east approach has closed the left turn from eastbound Tacoma to northbound at SE 6th Ave.  Left turns can be made at SE 7th Ave.

(more)

Sellwood Bridge Field Work Update for September 19

Tacoma St excavation 9-19-2014

Tacoma St excavation 9-19-2014

Field Work Update - September 19, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds westside retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.  On weekdays from Sept. 23 – Oct. 1, a third party contractor will be installing a fiber optic line under a closed traffic lane south of the bridge from 9 a.m. to 3 p.m.

Tacoma Street:  Reminder - Construction of the south side of the new bridge east approach has closed the left turn from eastbound Tacoma to northbound at SE 6th Ave.  Traffic control now allows eastbound travelers to turn left at SE 7th.  The south side of Tacoma is scheduled to be paved on September 25th, but traffic will not use that section until the new bridge opens.

Oktoberfest: Traffic in the project area may be heavier than normal Sept. 19 – 21 during the annual Oktoberfest celebration at Oaks Park.  Allow a bit more travel time during the event.

(more)

Sellwood Bridge Field Work Notice for Sept. 12

Bent 1 forms

Bent 1 forms

Field Work Update - September 12, 2014

TRAFFIC ALERTS

Hwy. 43 weeknight traffic impacts:  A reminder that Hwy. 43 lanes will be closed Monday to Friday from 7 p.m. to 5 a.m. the next several weeks during drilling work. Flaggers will direct traffic on the open lane. Travelers should expect delays during this night work.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds westside retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Tacoma St. traffic changes:  Reminder - Construction of the south side of the new bridge east approach has closed left turns from eastbound Tacoma to northbound SE 6th Ave. and SE 7th Ave. Eastbound travelers should use SE 9th Ave. as the detour to Spokane St.  This traffic change is in effect until the new bridge opens.  The south side of Tacoma will be paved later this month.

(more)

Sellwood Bridge Field Work Notice for September 5

Preparing eastside river pier for concrete pour

Preparing eastside river pier for concrete pour

Field Work Update - September 5, 2014

TRAFFIC ALERTS

Hwy. 43 weeknight traffic impacts:  A reminder that Hwy. 43 lanes will be closed Monday to Friday from 7 p.m. to 5 a.m. the next several weeks during drilling work. Flaggers will direct traffic on the open lane. Travelers should expect delays during this night work.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds westside retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Tacoma St. traffic changes:  Construction of the south side of the new bridge east approach has closed left turns from eastbound Tacoma to northbound SE 6th Ave. and SE 7th Ave. Eastbound travelers should use SE 9th Ave. as the detour to Spokane St.  This traffic change is in effect until the new bridge opens.  The south side of Tacoma will be paved later this month.

(more)

Sellwood Bridge field notice for August 29

Field Work Update - August 29, 2014

Note: Work will be suspended August 30-September 1 to observe Labor Day

TRAFFIC ALERTS

Tacoma St. change on Sept. 2:  Construction of the new bridge east approach will impact traffic starting Tuesday, Sept. 2. The left turn from eastbound Tacoma to northbound SE 6th Ave. will close after the Tuesday morning rush hour as the widening of Tacoma St. to the south begins. Travelers should use SE 9th Ave. as the detour to Spokane St.  This traffic change will remain in effect until the new bridge opens.  The south side of Tacoma will be paved later this month.

Spokane Street Parking: There will be a “No Parking” Zone established on September 4-5 from 8:00am – 5:00pm on the north curb line of Spokane from Oaks Park Way down to the river, to pothole for utilities.  At no time will driveways or streets be closed.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds westside retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Hwy 43 weeknight traffic impacts:  Crews will be drilling at night for 3 weeks, Monday-Friday, beginning on September 2, from 7 p.m. to 5 a.m.  Flaggers will control traffic. Travelers should expect multiple lane closures, flagger directing traffic and delays during this overnight work.

(more)

Sellwood Bridge Field Work Update for August 22

Retaining wall for interchange ramp

Retaining wall for interchange ramp

Field Work Update - August 22, 2014

TRAFFIC ALERTS

Westside work on August 25:  After the morning commute on Monday, the lanes of Hwy. 43 south of the Sellwood Bridge will be shifted to the west toward the new retaining walls (see photo).  This will allow crews to build the east side of the new interchange.  Expect traffic delays after 9 a.m. while crews move barricades, apply lane striping, and adjust overhead lights.  Motorists can avoid delays by using alternate routes such as the Ross Island Bridge or SW Terwilliger Blvd.

Tacoma St. change on Sept. 2:  Construction at the east end of the project will impact traffic starting Tuesday, Sept. 2. The left turn lane from eastbound Tacoma to 6th Ave. will close after the morning rush hour as the widening of Tacoma St. to the south begins.  9th Ave. is the recommended detour to Spokane St.  This traffic change will remain in effect until the new bridge opens.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the bridge while the contractor builds westside retaining walls.  A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for August 16

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the project limits south of the bridge while the contractor builds the retaining walls.   

A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. 

Upcoming Traffic change:  on Monday, August 25 southbound traffic lanes on Hwy. 43 south of the Sellwood Bridge will be shifted to the west toward the new retaining walls.  This will allow for crews to continue ramp work on the east side off Hwy. 43.  The shift will happen after the morning rush.  Expect delays while crews move barricades and apply final striping. Motorists should consider alternate routes during the late morning of Aug. 25th.

(more)

Sellwood Bridge Field Work Update for August 8

Installation of concrete girder for west approach span

Installation of concrete girder for west approach span

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the project limits south of the bridge while the contractor builds the retaining walls.   

  • On Saturday, August 9 from 7 a.m. to 4 p.m. one northbound lane will be closed near the cemetery entrance during preparation work for next week’s paving.
  • From Monday to Wednesday, August 11 – 13, paving and striping work south of the bridge will add to traffic congestion during the work day, due to trucks entering and exiting the work zone from the southbound lane and concrete barricades being moved. 

A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge traffic alert for Aug. 5 - 6

TRAFFIC ALERT

Traffic congestion is expected on the Sellwood Bridge and near the bridge on Highway 43 today and tomorrow from 9 a.m. to 4 p.m. due to heavy construction activity. Long trucks are delivering concrete girders on August 5 and 6 for the west approach to the new bridge, Other construction work requires a southbound lane of Highway 43 to be closed north and south of the bridge. Travelers may want to consider using alternate routes such as the Ross Island Bridge to avoid delays.


Sellwood Bridge Field Work Update for August 1

Bolt cluster for river pier angel wing

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the project limits south of the bridge while the contractor builds the retaining walls.

A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.

During daytime work hours on Tuesday and Wednesday, August 5 – 6, the northbound lane will be closed south of the bridge for placement of the Span 2 girders. The delivery trucks will travel north through the intersection and then back down the construction driveway at the former Staff Jennings entrance. After delivering their load, the trucks will re-enter northbound Hwy. 43 from the old Staff Jennings entrance.

(more)

Sellwood Bridge Field Work Update for July 28

View west from top of Bent 6 near east bank.

View west from top of Bent 6 near east bank.

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays until 4 p.m. between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls. Placement of the Span 2 girders on August 5 – 6 will require the outside northbound lane to be closed.

(more)

Sellwood Bridge Field Work Update for July 21

Sidewalk forms on east approach Span 10

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north and south of the bridge during excavation and ground anchor installation for the retaining walls.   On July 22 only, the bicycle/pedestrian path between the old Staff Jennings driveway and the entrance to Macadam Bay will be shifted west while a subcontractor does some exploratory work related to an underground waterline. Traffic lanes will be shifted to accommodate this work.

(more)

Sellwood Bridge Field Work Update for July 14

Columns for Hwy 43 interchange ramp

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for July 6

At east river pier, concrete forms for pier wall and angel wings

TRAFFIC ALERTS

Hwy. 43 weekday lane closures:

  • The outside northbound lane of Highway 43 will be closed south of the bridge during the day after 9 a.m. on Tuesday and Wednesday, July 8 – 9 when seventeen concrete girders are installed for Span 1.
  • The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.
(more)

Sellwood Bridge Field Work Update for June 27

Field Work Update - June 27, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 continues to be closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

Seventeen concrete girders will be installed for the first west side span on July 8 – 9. The northbound lane next to the span will be closed for this work.  The bridge will remain open. 

The project will be shut down July 4-6 for the Fourth of July holiday.   All lanes will be open unless emergencies arise.

(more)

Sellwood Bridge Field Work Update for June 20

Expanded waiting area at Hwy 43 crosswalk

Expanded waiting area at Hwy 43 crosswalk

Field Work Update - June 20, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Westside concrete pours for Sellwood Bridge work

Field Work Update - June 17, 2014

Two concrete pours for the new Sellwood Bridge will require longer work hours and some minor traffic impacts this week on the west side of the river:

Tuesday, June 17:  A pour for a retaining wall on the west side of Hwy. 43 south of the bridge will continue until about 8 p.m. tonight.  Flaggers will hold traffic when concrete trucks arrive or depart the site.  One southbound lane is closed until 4 p.m. One northbound lane is closed at the far south end of the project to provide a safe zone for the flaggers.  

Wednesday, June 18:  A concrete pour is scheduled to start in the early morning for the west river pier (Bent 4), where the first section of pier wall will be poured. Crews will arrive on the west side at 12:30 a.m. and concrete trucks will arrive starting at 2 a.m.  The operation is expected to end around noon.  Flaggers will need to hold traffic on Hwy. 43 when trucks arrive and exit the work zone north of the bridge.  All southbound lanes will be open to assist with traffic flow.  Lights will be needed for this night work.


Sellwood Bridge Field Work Update for June 13

Building work platform below east approach girders

Building work platform below east approach girders

Field Work Update - June 13, 2014

TRAFFIC ALERTS

Night work on Hwy. 43:  Installation of a storm drain line along Hwy. 43 south of the bridge will be completed Friday night, with working starting at 7 p.m. and ending by 6 a.m. Saturday. Flaggers direct traffic on a single lane during this work.

West wall concrete pour on June 16: An early morning concrete pour is scheduled on Monday for a retaining wall on the west side of Hwy. 43 south of the bridge. Crews will arrive at 4 a.m. with concrete trucks arriving at 5 a.m. One southbound lane and one northbound lane will be closed south of the bridge during the concrete pour. Flaggers will hold traffic when concrete trucks arrive on site.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for June 10

Pier caps of Bents 3 and 2

Pier caps of Bents 3 and 2

Field Work Update - June 10, 2014

TRAFFIC ALERTS

Night work on Hwy. 43:  Installation of a storm drain line along Hwy. 43 south of the bridge begins Wednesday evening.  Work hours are 7 p.m. to 6 a.m.  The work is expected to last up to five nights (Wednesday through Friday this week and Monday and Tuesday next week).  Flaggers will direct traffic on a single lane during this work.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for June 2

Building form for Bent 2 pier cap on west side

Building form for Bent 2 pier cap on west side

Field Work Update - June 2, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

Fiber Optic Night Work: A contractor will work at night June 3 and 4 (Tuesday and Wednesday), installing a fiber optic line along Hwy. 43 near the bridge.  The inside southbound lane will be closed during this work, which is not related to the Sellwood Bridge project.

(more)

Sellwood Bridge Field Work Update for May 27

Overhead welding unit with Sellwood steel

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

Fiber Optic Night Work: A contractor will work at night from May 26 – 28, Monday to Wednesday, installing a fiber optic line along Hwy. 43 near the bridge.  The inside southbound lane will be closed during this work, which should be completed next week.  This work is not related to the Sellwood Bridge project.

(more)

Sellwood Bridge Field Work Update for May 20

Offloading girder from truck

Offloading girder from truck

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is closed weekdays from 9 a.m. to 4 p.m. north of the bridge during excavation and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for May 12

Sellwood dive team

TRAFFIC ALERTS

Bridge Closure May 13 – 16: The Sellwood Bridge will be closed from 7 p.m. on Tuesday, May 13 until as late as 4 p.m. on Friday, May 16 to allow the contractor to install pre-cast concrete girders on the east approach for the new bridge. (Learn why these girders are built offsite on our website.)

The bridge will be closed to all traffic modes (motor vehicles, bicyclists and pedestrians) around the clock during the girder installation. Hwy. 43 will remain open. The Ross Island Bridge is the northern detour for motor vehicles, and the Hawthorne Bridge is a good alternate route for bicyclists. Congestion on detour routes is expected during commute hours, so please allow more time for your trip when the bridge is closed.

Springwater Trail users may experience brief delays Thursday and Friday when girders are installed over the trail. Flaggers will direct trail traffic on these dates and a short detour will be available via SE 6th Avenue.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to earthwork and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for May 5

Bee swarm on west work bridge

TRAFFIC ALERTS

Lane Striping: The contractor re-striped crosswalks and lane markings at the west end of the bridge at Hwy. 43 last week to improve their visibility.

Bridge Closure May 13 – 16: The Sellwood Bridge will be closed from 7 p.m. on Tuesday, May 13 until as late as 4 p.m. on Friday, May 16 to allow the contractor to install pre-cast concrete girders on the east approach for the new bridge. (Learn why these girders are built offsite on our website.)

The trucks that will deliver the girders are 140 feet long. The bridge will be closed to all traffic modes (motor vehicles, bicyclists and pedestrians) around the clock during the girder installation. Hwy. 43 will remain open. Springwater Trail users may experience brief delays May 15 – 16 when the girders are installed over the trail. Flaggers will direct trail traffic on these dates and a short detour will be available via SE 6th Avenue.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to earthwork and ground anchor installation for the retaining walls.

(more)

Sellwood Bridge Field Work Update for April 28

Pouring concrete for west side columns

TRAFFIC ALERTS

Bridge Closure May 13 – 16: The Sellwood Bridge will be closed from 7 p.m. on Tuesday, May 13 until as late as 4 p.m. on Friday, May 16 to allow the contractor to install pre-cast concrete girders on the east approach for the new bridge. (To learn why these girders are built offsite, see the new article on our website.)

The trucks that will deliver the girders are 140 feet long. The bridge will be closed to all traffic modes (motor vehicles, bicyclists and pedestrians) around the clock during the girder installation. Springwater Trail users may experience brief delays under the bridge May 15 – 16 when the girders are installed over the trail. Flaggers will direct trail traffic on these dates and a short detour will be available via SE 6th Avenue.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to earthwork and ground anchor installation for the retaining walls.

Water Line Relocation: The first phase of a water line relocation along Hwy. 43 was tied in last week and the new line was flushed over the weekend. Paving and re-striping on April 28 – 29 will impact traffic during off peak daytime hours. The second phase of the water line relocation will take place north of the bridge later this year and will not impact traffic.

Lane Striping: Weather permitting, the contractor will install new lane striping on Hwy. 43 on Tuesday, April 29 after 9 a.m.


(more)

Sellwood Bridge Field Work Update for April 22

Rebar columns at Bent 3 on west bank

TRAFFIC ALERTS

Bridge Closure May 13 – 16: The Sellwood Bridge is scheduled to be closed from 7 p.m. on Tuesday, May 13 until as late as 4 p.m. on Friday, May 16 to allow the contractor to install pre-cast concrete girders on the east approach for the new bridge.  The trucks that will deliver the girders are 140 feet long.  The bridge will be closed to all traffic modes (motor vehicles, bicyclists and pedestrians) around the clock during the installation of the girders.  Detour signs will be posted.  Springwater Trail users may experience brief delays under the bridge May 15 – 16 when the girders are installed over the trail.  Flaggers will direct trail traffic on these dates and a short detour will be available via SE 6th Avenue.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to earthwork and ground anchor installation for the retaining walls.

Water Line Relocation: The first phase of a water line relocation along Hwy. 43 has been completed.  A City of Portland crew is testing the line, which could be connected at night this week.  One lane will be closed during the night work.

Lane Striping: Weather permitting, the contractor will install new lane striping on Hwy. 43 from April 24 – 30, during off peak hours.

(more)

Sellwood Bridge Field Work Update for April 14

Formwork for west bridge abutment

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 remains closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to earthwork and ground anchor installation for the retaining walls.

Water Line Relocation: Relocation of a 16 inch water line along Hwy. 43 south of the bridge continues during the day through April 18. No night work is scheduled this week.

(more)

Sellwood Bridge Field Work Update for April 7

Installing ground anchors for westside wall.

Installing ground anchors for westside wall.

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 remains closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls for the next several weeks. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to earthwork and anchor installation on the retaining walls.

Water Line Relocation: Relocation of a 16 inch water line along Hwy. 43 south of the bridge continues during the day and at night from 7 p.m. to 6 a.m. to minimize disruption of commuter traffic. At night flaggers will direct traffic in a single open lane. Work lights are used for safety. The work will continue through April 18.

(more)

Sellwood Bridge Field Work Update for March 31

Night concrete pour for Bent 3 footing

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 remains closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

Water Line Relocation: Relocation of a 16 inch water line along Hwy. 43 south of the bridge has begun (see photo).  The work is being done during the day and at night from 7 p.m. to 6 a.m. to minimize disruption of commuter traffic.  At night flaggers will direct traffic in a single open lane.  Work lights are used for safety. The work will continue for several weeks.

(more)

Sellwood Bridge Construction Traffic Alert for March 28 - 29

March 27, 2014

Traffic on Highway 43 near the Sellwood Bridge will be impacted by a major concrete pour scheduled for the new bridge on Friday and Saturday, March 28–29.  About 250 concrete truck deliveries will be required over a 36-hour period to pour the footing for a column near the west bank of the river.  Work begins at 2 a.m. Friday and could last until Saturday afternoon. Twenty-five hundred cubic yards of concrete will be poured in a continuous operation.  Work lights will be needed at night.

Trucks will access the site from Highway 43, traveling south from the Ross Island Bridge and turning left into the work zone entrance south of the Sellwood Bridge.  The outside northbound lane will be closed north and south of the bridge to allow flaggers to hold northbound traffic when trucks arrive and to allow trucks to quickly exit the work site. Both southbound lanes of Highway 43 will remain open to improve traffic flow. 

Traffic congestion may increase during the Friday morning and afternoon commutes. Drivers may want to consider alternate routes such as SW Taylors Ferry Road or SW Terwilliger Blvd. to avoid delays. 

The footing will support two steel arch river spans on the west bank and four lanes of bridge traffic above.


Sellwood Bridge Field Work Update for March 24

Tying rebar for westside retaining walls

Tying rebar for westside retaining walls

Due to a recent schedule change, the weekly Field Work Update will typically be sent each Monday instead of Friday, effective today.

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 remains closed weekdays (except from 4 p.m. to 7 p.m. and on Friday, March 28) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

Water Line Relocation: A major task for the project this spring is relocating a 16 inch water line that runs along Hwy. 43, providing water service to the Riverdale area.  The line needs to be relocated due to construction of the new interchange.  Installation of the new line south of the bridge begins on March 24 and will last for at least one month.  This work will happen within the closed traffic lanes at first.  In April night-time lane closures will be required.

Westside Concrete Pour March 28 – 29:  One of the largest concrete pours of the project starts Friday, March 28 at 2 a.m. and continues until Saturday afternoon.  About 250 concrete truck deliveries will be needed for the massive footing at Bent 3, which will support the steel arch spans on the west bank of the river and four lanes of traffic above.  Trucks will arrive from the north and turn left into the work zone from Hwy. 43 south of the bridge.  Both southbound lanes will be open during the pour to improve traffic flow.

Oaks Park Spring Break Traffic:  With Oaks Park open for Spring Break this week, traffic has been heavier than normal during the day.  Please allow extra time for day time trips in the project area this week.

(more)

Sellwood Bridge Field Work Update for March 14

Lowered perched box caisson for Bent 5

Lowered perched box caisson for Bent 5

Field Work Update - March 14, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 remains closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

(more)

Sellwood Bridge Field Work Update for March 7

Drilling shafts for ramp of new interchange

Drilling shafts for ramp of new interchange

Field Work Update - March 7, 2014

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

(more)

Sellwood Bridge Field Work Update for February 28

Concrete pour for Bent 6 Columns 2-13-2014

Concrete pour for Bent 6 Columns 2-13-2014

Field Work Update - February 28, 2014

TRAFFIC ALERTS

Fallen Trees:  Traffic on the bridge and Hwy. 43 was slowed on February 24 – 25 after strong wind gusts toppled trees onto Hwy. 43 and Hwy. 99E, outside our project limits.  One incident closed Hwy. 43 for several hours south of the bridge.  Recent rains have saturated the ground, leading to more downed trees during windstorms.  Please drive with caution during windstorms.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

Other Projects: Two other projects are impacting traffic on Hwy. 43 north of the bridge.  Neither is related to Sellwood Bridge work.  Portland General Electric crews will work at the intersection of Hwy. 43 and SW Taylors Ferry/SW Miles St. on Friday, February 28 from 9 a.m. to 3 p.m. and Sunday, March 2 from 7 a.m. to 2 p.m. The work will require a northbound lane closure on Friday and the traffic signal will need to be turned off on Sunday, when flaggers will direct traffic.  

Meanwhile, a short section of sidewalk next to Freeman Motors along the east side of Hwy. 43 is being repaired.  Sidewalk users should follow the detour signs around the sidewalk closure, via the parking lot.   This work should be completed in the next few days.

(more)

Sellwood Bridge Field Work Update for February 21

Setting forms at Bent 3, westside

Setting forms at Bent 3, westside

Field Work Update - February 21, 2014

Related articles

TRAFFIC ALERTS

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

(more)

Sellwood Bridge to reopen for morning commute on Tuesday, February 18

Field Work Update - February 18, 2013

Related article

The Sellwood Bridge will reopen to traffic ahead of schedule on February 18. The bridge has been closed since midnight on Friday while a contractor drilled shafts under traffic lanes at the west end of the bridge.  The bridge will reopen to motor vehicles, bicyclists and pedestrians by 7 a.m. on Tuesday, February 18.  

The contractor had been given permission to keep the bridge closed until as late as 5 a.m. on February 20 to complete the work.  The drilling team worked around the clock from midnight on Friday and encountered no major obstacles during the operation.  A line of steel soldier piles were installed under the traffic lanes for a wall that will support a new Highway 43 interchange with the bridge.


Sellwood Bridge Field Work Update for February 14

Diagram of Sellwood Bridge closure Feb 15 - 20

Diagram of Sellwood Bridge closure Feb 15 - 20

Field Work Update - February 14, 2014

Construction activity took a rare timeout during last week’s snow storm.  Field work resumed on Tuesday.

TRAFFIC ALERTS

February 15 - 20 bridge closure:  The Sellwood Bridge will close at 12:01 a.m. on Saturday, February 15 and reopen by 5 a.m. on Thursday, February 20 to allow installation of steel soldier piles for a wall of the new interchange at the west end of the bridge.  Rainy weather will not impact the work.  The closure will affect all traffic modes, including bicyclists and pedestrians.  Hwy. 43 will remain open.  The Westside bicycle and pedestrian trail will be closed between the bridge and the Macadam Bay driveway during the work, so trail users will need to use an alternate route.  The contractor will work around the clock during the closure.  The noise level will be similar to the west side night work last month.  See our news release for more information about the closure and alternate routes.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

(more)

Traffic changes for Sellwood Bridge closure February 15 - 20

Diagram of Sellwood Bridge closure Feb 15 - 20

Diagram of Sellwood Bridge closure Feb 15 - 20

Traffic changes are in store for Sellwood Bridge users when the bridge is closed for construction February 15 - 20.  The bridge is scheduled to close at 12:01 a.m. on Saturday and reopen by 5 a.m. on Thursday.  The closure will allow a contractor to install steel soldier piles across traffic lanes at the west end of the bridge.  The piles will support the walls of a new two-level interchange where the bridge connects with Highway 43.  The closure is scheduled over a holiday weekend to minimize the number of commute days that the bridge is closed.

Highway 43 will remain open to two-way traffic at all times while the bridge is closed.  Turn lanes from Highway 43 to the bridge will be closed and used by construction vehicles only.

The bridge will be closed to motor vehicles, bicyclists and pedestrians.

(more)

Sellwood Bridge Field Work Update for January 31

Placing forms for wall fascia, Jan 2014

Placing forms for wall fascia, Jan 2014

Field Work Update - January 31, 2014

TRAFFIC ALERTS

February bridge closure:  The Sellwood Bridge will close at 12:01 a.m on Saturday, February 15 and reopen by 5 a.m. on Thursday, February 20 to allow work on a retaining wall for the new interchange at the west end of the bridge.  (We adjusted the start date by one minute to avoid confusion about the date.) The closure will affect all traffic modes, including bicyclists and pedestrians.  Hwy. 43 will remain open.  The contractor will work around the clock during the closure.  The noise level will be similar to the west side night work last month.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls. A northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls. The City of Portland has adjusted the traffic signal at the west end of the bridge to improve traffic flow.

(more)

Sellwood Bridge Field Work Update for January 24

Jacking team for lowering box caisson

Jacking team for lowering box caisson

Field Work Update - January 24, 2014

Related article

Sellwood Bridge update: Crews install first box caisson in Willamette River (photo gallery and video) - OregonLive.com

TRAFFIC ALERTS

February bridge closure: The Sellwood Bridge is scheduled to close at midnight on Friday, February 14 and reopen by 5 a.m. on Thursday, February 20 to allow work on a retaining wall for the new interchange at the west end of the bridge. The closure will affect all traffic modes, including bicyclists and pedestrians. Hwy. 43 will remain open.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls on the west side of Hwy. 43. Through January a northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

(more)

Sellwood Bridge Field Work Update for January 17

Field Work Update - January 17, 2014

TRAFFIC ALERTS

New dates for February bridge closure:  The Sellwood Bridge closure has been rescheduled to start at midnight on Friday, February 14 and end by 5 a.m. on Thursday, February 20.  The dates were shifted to avoid closing the bridge on Valentine’s Day and negatively impacting local restaurants and retailers. The closure still includes two normal commuting days (February 18 – 19).  February 17 is a public holiday.  

A few road signs with the old closure dates are being updated.

The closure will affect all traffic modes, including bicyclists and pedestrians.  It will allow the contractor to work on a wall for the new interchange.  Hwy. 43 will remain open during the closure. 

New Traffic Signal:  Please note that the only signal phase that requires westbound bridge traffic to stop at the west end of the bridge is when a pedestrian or bicyclist activates the signal to use the crosswalk.  The signal is often turned off on weekdays between 9 a.m. and 4 p.m. when flaggers direct traffic.  This week new curbing and lane delineation were added to the interchange.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls on the west side of Hwy 43. Through January a northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge due to work on the retaining walls.

(more)

Sellwood Bridge Field Work Update for January 10

Bent 6 concrete pour on eastside

Bent 6 concrete pour on eastside

Field Work Update - January 10, 2014

TRAFFIC ALERTS

New Traffic Signal: The timing of the new signal at the west end of the bridge and Hwy. 43 was adjusted this week to improve traffic flow through the intersection.  The only signal phase that requires westbound bridge traffic to stop is activated by a pedestrian or bicyclist to use the crosswalk across the bridge lanes.  The signal is often turned off on weekdays between 9 a.m. and 4 p.m. when flaggers direct traffic.  Additional curbs and lane markings will be installed on Hwy. 43 north of the bridge next week.

Eastside Concrete Pour January 10 – 11: About 200 concrete truck deliveries will be made to the east work zone from 2 p.m. on January 10 until 2 p.m. on January 11.  A truck will arrive about every eight minutes using a route from Tacoma St. to SE 6th Ave. to Spokane St. to the work zone entrance.  Flaggers will direct traffic and on-street parking will be removed on Spokane between Oaks Park Way and SE 6th Ave.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls on the west side of Hwy 43. Through January a northbound lane is also closed weekdays from 9 a.m. to 4 p.m. north of the bridge and the traffic signal at the west end of the bridge is turned off due to work on the retaining walls.

February bridge closure:  The Sellwood Bridge is scheduled to close from 5 a.m. on February 13 until as late as 5 a.m. on February 18.  The closure will allow the contractor to work on a wall for the new interchange.  Hwy. 43 will remain open during the closure.

(more)

Sellwood Bridge Field Work Update for January 3

Open zone after demolition of Hwy 43 slip lane

Open zone after demolition of Hwy 43 slip lane

Field Work Update - January 3, 2014

TRAFFIC ALERTS

Westside concrete pours: Concrete pours for foundation shafts for the new northeast highway ramp are planned on January 6 from noon until about 4 pm and on January 10.  A traffic lane will be closed for these pours.

New traffic signal at Highway 43: This week lane striping and pavement markings were touched up at the intersection, one of several changes that are being made to improve traffic flow at the new traffic signal.

Night lane closures on Hwy. 43:  Lanes will be closed tonight and on weeknights next week on Hwy. 43 north and south of the bridge for installation of steel piles.  One lane will remain open in each direction from 7 p.m. until 6 a.m.  The night work should be completed next week. The traffic signal is turned off during this work and flaggers direct traffic.

Hwy. 43 weekday lane closures: The outside southbound lane of Hwy. 43 is closed weekdays (except from 4 p.m. to 7 p.m.) between SW Taylors Ferry Road and the project limits south of the bridge while the contractor works on retaining walls on the west side of Hwy 43.

(more)