Why is it needed? Project Phases The New Bridge and Interchange The Detour Bridge Sustainability Diversity Program Field Work and Construction Updates Contractor Information
Past Events and Activities Past Committee Meetings School-Based Outreach Program
Library Newsroom Photo and Image Gallery EIS Documents Links Frequently Asked Questions
Overview Before the Bridge Bridge Fever! The Great Bridge Scandal Gustav Lindenthal Construction and Dedication Need for Replacement River View Cemetery

Field Work and Construction Updates

This page provides updates about bridge construction that may impact bridge users and immediate neighbors. To join the Construction Updates email list, please fill out the form on the right.

Sellwood Bridge Field Work Notice for March 27

Installing rebar for crossbeam on east approach, 3-2015

Installing rebar for crossbeam on east approach, 3-2015

Field Work Notice - March 27, 2015

TRAFFIC ALERTS

April 17 – 20 Bridge Closure: The contractor plans to close the bridge to all traffic from 7 pm on Friday, April 17 until as late as 6 am on Monday, April 20 to implement a traffic pattern change at the west end of the bridge and install deck girders for the east approach.  When the bridge reopens, traffic will use the new west approach which will transition onto the detour bridge. This will allow construction of the ramp from the bridge to northbound Hwy. 43. Highway traffic will not be impacted by the bridge closure.

Hwy. 43 traffic impacts:

  • Lane closures are planned from 9 am to 4 pm next week in the southbound outside lane north and south of the bridge during finish work on retaining walls and installation of gutters behind the walls.
  • The outside northbound lane will be closed next week from 7 am to 4 pm between the bridge and Freeman Motors during work to connect the new 36-inch waterline.
(more)

Bridge Closure: April 17 - 20

Construction Notice - March 24, 2015

The contractor plans to close the bridge to all traffic from 7 pm on Friday, April 17 until as late as 6 am on Monday, April 20 to implement a traffic pattern change at the west end of the bridge.  When the bridge reopens on April 20, traffic will use the new west approach which will transition onto the detour bridge. This will allow construction of the ramp from the bridge to northbound Hwy. 43. Highway traffic will not be impacted by the weekend bridge closure.


Sellwood Bridge Field Work Notice for March 20

Arch segments installed in sequence, 3-2015

Arch segments installed in sequence, 3-2015

Field Work Notice - March 20, 2015

TRAFFIC ALERTS

April Bridge Closure: The contractor plans to close the bridge to all traffic from 7 pm on Friday, April 17 until as late as 6 am on Monday, April 20 to implement a traffic pattern change at the west end of the bridge.  When the bridge reopens on April 20, traffic will use the new west approach which will transition onto the detour bridge. This will allow construction of the ramp from the bridge to northbound Hwy. 43. Highway traffic will not be impacted by the weekend bridge closure.

Bridge delays on March 24:  Sellwood Bridge traffic will be delayed at times on Tuesday between 9 am and 4 pm during installation of heavy steel segments for one of the arch spans. Delays of up to 20 minutes (including sidewalks) may be needed. Bridge users may want to consider alternate routes to avoid delays.

Hwy. 43 traffic impacts:

  • Lane closures are planned from 9 am to 4 pm next week in the southbound outside lane south of the bridge during finish work on the concrete walls.
  • The outside northbound lane will be closed next week from 7 am to 4 pm north of the bridge during work to connect the new 36-inch waterline.

Springwater Trail:  The trail will be closed under the bridge from 7:30 am to 4 pm Wednesday to Friday, March 25 – 27 during work on the east abutment wall.  Flaggers will direct trail users to the alternate route on SE 7th Ave. where a crosswalk crosses SE Tacoma St.

(more)

Sellwood Bridge Field Work Notice for March 13

Span 2 deck concrete pour

Span 2 deck concrete pour

Field Work Notice - March 13, 2015

TRAFFIC ALERTS

Bridge traffic delays:  Sellwood Bridge traffic will be delayed at times on Monday, March 16 between 9 am and 4 pm during installation of heavy steel arch segments for the east span of the new bridge.  Delays of up to 20 minutes (including sidewalks) may be needed during installation. Bridge users may want to consider alternate routes to avoid delays.

Hwy. 43 traffic impacts:

  • Lane closures are planned next week in the southbound outside lane north of the bridge during finish work on the concrete walls.
  • Lane closures are planned next week for northbound traffic south of the bridge during installation of large concrete blocks for a new retaining wall.

Springwater Trail:  On Saturday morning, March 14 the trail will be closed under the bridge during installation of panels for the east abutment wall.  Signs will direct trail users to the alternate route.

(more)

Sellwood Bridge Field Work Notice for March 6

Setting rebar for east approach crossbeam

Setting rebar for east approach crossbeam

Field Work Notice - March 6, 2015

TRAFFIC ALERTS

Bridge traffic delays:  Sellwood Bridge traffic will be delayed at times March 9 – 11 during installation of heavy steel arch segments for the east span of the new bridge.  Delays of up to 20 minutes (including sidewalks) may be needed at these times: Monday from 12 – 4 pm; Tuesday from 9 am to noon; Wednesday from 9 to 4 pm. Bridge users may want to consider alternate routes to avoid delays.

Hwy. 43 traffic impacts:

  • Lane closures are expected next week in the southbound outside lane north of the bridge during finish work on the concrete walls.
  • Lane closures are expected next week for northbound traffic south of the bridge during delivery and installation of large concrete blocks for a new retaining wall.
(more)

Sellwood Bridge Field Work Notice for February 27

Moment slab along edge of southeast ramp

Field Work Notice - February 27, 2015

TRAFFIC ALERTS

Hwy. 43 traffic impacts: Lane closures are expected next week in the southbound outside lane north and south of the bridge to install street light poles, traffic signal poles and aerial spans. A new traffic signal is being set up for the next traffic stage in May. That stage will shift traffic onto the west end of the new bridge, to allow the northbound ramp to be built.

South of the bridge the outside northbound lane will be closed at times next week when large concrete blocks will be offloaded and installed for a retaining wall on the southeast ramp.

A major concrete pour is planned on Wednesday, March 4 for the deck of Span 2, with increased concrete truck deliveries that day.

North of the bridge, trail and motor vehicle traffic may experience brief delays due to waterline work along the east edge of Hwy. 43. Flaggers will direct trail traffic at times.

Spokane Street/6th Ave. Parking: A no parking zone will be established on March 5 – 6 at locations along SE 6th Ave. near SE Spokane St. and on Spokane between 6th Ave. and SE Oaks Parkway. The parking spaces need to be closed on days when large construction cranes will be delivered for erection of the east side steel arch span.

(more)

Sellwood Bridge Field Work Notice for February 20

Trail through waterline work zone north of bridge

Field Work Notice - February 20, 2015

TRAFFIC ALERTS

Hwy. 43 traffic impacts: Trail and motor vehicle traffic north of the bridge may experience brief delays next week due to waterline work along the east edge of Hwy. 43. The outside northbound lane will be closed at some off-peak times to allow exiting dump trucks to accelerate safely onto the highway (see photo). Trail users may be asked to wait at times for trucks and equipment to be cleared from the trail.

City Sewer Project on Taylors Ferry Road: Many people contacted us this week to ask about new construction signs seen on Taylors Ferry Road. These are for a City of Portland sewer project that is not related to the Sellwood Bridge project. The City project will require Taylors Ferry Road between Macadam Ave. and nearby Stephens Creek to be closed on weeknights from 8 pm to 6 am starting Feb. 23 for up to four months. For more information, visit the project website.

(more)

Sellwood Bridge Field Work Notice for February 13

Demolishing Hwy 43 retaining wall

Demolishing Hwy 43 retaining wall

Field Work Notice - February 13, 2015

TRAFFIC ALERTS

Hwy. 43 traffic impacts: There will be short-term closures of the outside southbound lane north of the bridge for installation of streetlight pole foundations and lights. Trail traffic north of the bridge may experience brief delays next week due to waterline work along the east edge of Hwy. 43.  The outside northbound lane will be closed at some off-peak times to allow exiting dump trucks to accelerate safely onto the highway.

(more)

Sellwood Bridge Field Work Notice for February 6

Installation of waterline north of bridge

Installation of waterline north of bridge

Field Work Notice - February 6, 2015

TRAFFIC ALERTS

Hwy. 43 traffic impacts: There will be short-term closures of lanes near the west end of the bridge at times next week during installation of two traffic signal poles. Trail traffic just north of the bridge may experience brief delays next week due to waterline work along the east edge of Hwy. 43.  Flaggers will direct trail traffic at these times. Additional lane closures may be needed on Hwy. 43 during off-peak hours next week.

(more)

Sellwood Bridge construction traffic alert for February 4

Related articles

Traffic on Highway 43 near the Sellwood Bridge will be impacted by construction activity most of the day on Wednesday, February 4. Work will begin before the morning commute and may continue into the evening. A contractor will need to shift traffic lanes and perform a number of tasks as highway lanes north of the bridge shift west against new retaining walls. A concrete pour for the new bridge is also scheduled. Drivers should expect delays on the bridge and Highway 43 throughout the day as crews remove old striping, add new striping, install barriers and fencing. The shift will allow crews to construct the east side of the interchange. Drivers may want to use alternate routes such as the Ross Island Bridge or SW Terwilliger Blvd. on Wednesday.


Browse previous entries: